Datacenter Sites in Comal County, Texas
Comal County has 49 scored datacenter candidate sites averaging 61.1/100 DC Readiness, with a catalogued aggregate of 7,100 MW. FEMA rates local natural-hazard risk as "Very High". The county has a datacenter tax incentive on record.
49
Candidate sites
61.1/100
Avg DC Readiness
7,100 MW
Catalogued capacity
theoretical aggregate
Very High
Hazard rating
Site-selection context for Comal County
Yessales_tax_exemption
Datacenter tax incentive
11.45¢/kWh
Commercial electricity
7.43¢/kWh
Industrial electricity
10
Fiber providers
Medium-High
Water stress
$5,507
Land price / acre
2,600
Cooling degree days
1,800
Heating degree days
65°F
Mean annual temp
Incentive detail: Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.
By site type
Top datacenter sites in Comal County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| PARKWAY | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 69.3 |
| CIBOLO CREEK | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 68.9 |
| TRI-COUNTY | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 68.1 |
| BULVERDE | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 67.8 |
| SCHERTZ | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 66.7 |
| WEIDERSTEIN | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 66.6 |
| TAP316228 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 66.3 |
| LOOP 337 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 66.3 |
| SHERIFFS POSSE | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 66.1 |
| TAP316231 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 65.9 |
| Greenfield (ELM CREEK - HILL COUNTRY 345) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 65.9 |
| Greenfield (HAYS ENERGY - KENDALL) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 65.6 |
| GREEN MOUNTAIN | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 65.5 |
| HIGHWAY 46 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 65.5 |
| TAP316230 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 65.4 |
| TXI | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 65.3 |
| HENNE | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 65.3 |
| CEMEX | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 65.3 |
| TAP316232 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 65.1 |
| FISCHER | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 65.0 |
| HUNTER | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 65.0 |
| RIVER OAKS | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 64.9 |
| UNKNOWN308555 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 64.7 |
| SATTLER | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 64.5 |
| Greenfield (HAYS ENERGY - KENDALL) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 64.3 |
Comal County datacenter FAQ
- How many datacenter sites are in Comal County?
- 49 scored datacenter candidate sites, averaging 61.1/100 DC Readiness.
- Does Comal County offer datacenter tax incentives?
- Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.
- What is the natural-hazard risk in Comal County?
- FEMA's National Risk Index rates Comal County as "Very High" (score 55).
- What are industrial electricity rates in Comal County?
- Average industrial electricity is 7.43¢/kWh and commercial is 11.45¢/kWh in Comal County.