Datacenter Sites in Bastrop County, Texas
Bastrop County has 43 scored datacenter candidate sites averaging 57.7/100 DC Readiness, with a catalogued aggregate of 13,000 MW. FEMA rates local natural-hazard risk as "Very High". The county has a datacenter tax incentive on record.
43
Candidate sites
57.7/100
Avg DC Readiness
13,000 MW
Catalogued capacity
theoretical aggregate
Very High
Hazard rating
Site-selection context for Bastrop County
Yessales_tax_exemption
Datacenter tax incentive
8.49¢/kWh
Commercial electricity
9.30¢/kWh
Industrial electricity
8
Fiber providers
Medium-High
Water stress
$6,225
Land price / acre
2,600
Cooling degree days
1,800
Heating degree days
65°F
Mean annual temp
Incentive detail: Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.
By site type
Top datacenter sites in Bastrop County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| UNKNOWN306282 | Substation-Adjacent | 345 kV | 600 MW | 3.4 yrs | 70.4 |
| LOST PINE | Substation-Adjacent | 345 kV | 600 MW | 3.4 yrs | 68.5 |
| WYLDWOOD | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 64.8 |
| TAHITIAN VILLAGE | Substation-Adjacent | 345 kV | 600 MW | 3.4 yrs | 64.2 |
| Greenfield (AUSTROP - UNKNOWN301186) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 63.6 |
| Greenfield (AUSTROP - LOST PINE) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 63.3 |
| UNKNOWN307470 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 63.2 |
| TAP310549 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 63.1 |
| UNKNOWN302193 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 63.0 |
| UNKNOWN307584 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 62.9 |
| Greenfield (UNKNOWN301015 - AUSTROP) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 62.8 |
| BASTROP WEST | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 62.7 |
| BLUEBONNET | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 62.7 |
| Greenfield (UNKNOWN301015 - AUSTROP) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 62.6 |
| Greenfield (UNKNOWN300587 - SIM GIDEON) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 62.2 |
| Greenfield (FAYETTE PLANT #2 - LYTTON SPRI) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 62.0 |
| Greenfield (SIM GIDEON - ELGIN SWITCHING) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 61.9 |
| Greenfield (UNKNOWN306282 - TAHITIAN VILLA) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 61.6 |
| Greenfield (FAYETTE PLANT #2 - LYTTON SPRI) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 60.8 |
| Greenfield (UNKNOWN307818 - LYTTON SPRINGS) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 60.3 |
| UNKNOWN309921 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 59.5 |
| Greenfield (LOST PINE - AUSTROP) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 58.4 |
| Greenfield (UNKNOWN300587 - SIM GIDEON) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 58.3 |
| Greenfield (UNKNOWN307818 - LYTTON SPRINGS) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 58.2 |
| Greenfield (SIM GIDEON - ELGIN SWITCHING) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 58.2 |
Bastrop County datacenter FAQ
- How many datacenter sites are in Bastrop County?
- 43 scored datacenter candidate sites, averaging 57.7/100 DC Readiness.
- Does Bastrop County offer datacenter tax incentives?
- Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.
- What is the natural-hazard risk in Bastrop County?
- FEMA's National Risk Index rates Bastrop County as "Very High" (score 55).
- What are industrial electricity rates in Bastrop County?
- Average industrial electricity is 9.30¢/kWh and commercial is 8.49¢/kWh in Bastrop County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Bastrop County, Texas. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.