Datacenter Sites in Miami County, Ohio
Miami County has 41 scored datacenter candidate sites averaging 53.5/100 DC Readiness, with a catalogued aggregate of 2,000 MW. FEMA rates local natural-hazard risk as "Relatively Moderate". The county has a datacenter tax incentive on record.
41
Candidate sites
53.5/100
Avg DC Readiness
2,000 MW
Catalogued capacity
theoretical aggregate
Relatively Moderate
Hazard rating
Site-selection context for Miami County
Yessales_tax_exemption
Datacenter tax incentive
10.30¢/kWh
Commercial electricity
7.80¢/kWh
Industrial electricity
10
Fiber providers
Low
Water stress
$10,549
Land price / acre
900
Cooling degree days
5,400
Heating degree days
51°F
Mean annual temp
Incentive detail: DC sales tax exemption on equipment and electricity (2022 law); JobsOhio grants.
By site type
Top datacenter sites in Miami County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| MIAMI | Substation-Adjacent | 345 kV | 600 MW | 3.8 yrs | 63.3 |
| WEST MILTON | Substation-Adjacent | 345 kV | 600 MW | 3.8 yrs | 62.7 |
| EC Near Piqua Power Plant | Greenfield | — | — | 3.2 yrs | 58.7 |
| EC Near Piqua Power Plant | Greenfield | — | — | 3.2 yrs | 58.0 |
| NEW CARLISLE | Substation-Adjacent | 138 kV | 100 MW | 3.8 yrs | 57.1 |
| EC Near Piqua Power Plant | Greenfield | — | — | 3.2 yrs | 57.0 |
| EC Near Piqua Power Plant | Greenfield | — | — | 3.2 yrs | 57.0 |
| EC Near Piqua Power Plant | Greenfield | — | — | 3.2 yrs | 56.9 |
| STAUNTON | Substation-Adjacent | 138 kV | 100 MW | 3.8 yrs | 56.8 |
| EC Near Piqua Power Plant | Greenfield | — | — | 3.2 yrs | 56.7 |
| TAP141226 | Substation-Adjacent | 138 kV | 100 MW | 3.8 yrs | 56.6 |
| ELDEAN | Substation-Adjacent | 138 kV | 100 MW | 3.8 yrs | 56.6 |
| TAP141227 | Substation-Adjacent | 138 kV | 100 MW | 3.8 yrs | 56.4 |
| EC Near Piqua Power Plant | Greenfield | — | — | 3.2 yrs | 56.1 |
| EC Near Piqua Power Plant | Greenfield | — | — | 3.2 yrs | 55.8 |
| UNKNOWN141228 | Substation-Adjacent | 138 kV | 100 MW | 3.8 yrs | 55.4 |
| UNKNOWN113861 | Substation-Adjacent | 69 kV | 50 MW | 3.8 yrs | 55.3 |
| EC Near Piqua Power Plant | Greenfield | — | — | 3.2 yrs | 55.3 |
| UNKNOWN112951 | Substation-Adjacent | 69 kV | 50 MW | 3.8 yrs | 55.3 |
| PIQUA POWER PLANT | Substation-Adjacent | 69 kV | 50 MW | 3.8 yrs | 54.8 |
| EC Near Piqua Power Plant | Greenfield | — | — | 3.2 yrs | 54.4 |
| EC Near Piqua Power Plant | Greenfield | — | — | 3.2 yrs | 53.7 |
| UNKNOWN113852 | Substation-Adjacent | 69 kV | 50 MW | 3.8 yrs | 53.0 |
| West Milton Pure Gas Station | Industrial | — | — | 3.8 yrs | 50.3 |
| Mine Site | Former Mine | — | — | 3.8 yrs | 50.1 |
Miami County datacenter FAQ
- How many datacenter sites are in Miami County?
- 41 scored datacenter candidate sites, averaging 53.5/100 DC Readiness.
- Does Miami County offer datacenter tax incentives?
- DC sales tax exemption on equipment and electricity (2022 law); JobsOhio grants.
- What is the natural-hazard risk in Miami County?
- FEMA's National Risk Index rates Miami County as "Relatively Moderate" (score 30).
- What are industrial electricity rates in Miami County?
- Average industrial electricity is 7.80¢/kWh and commercial is 10.30¢/kWh in Miami County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Miami County, Ohio. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.