Skip to content
Gridcensus

Datacenter Sites in McLean, North Dakota

McLean has 27 scored datacenter candidate sites averaging 57.7/100 DC Readiness, with a catalogued aggregate of 2,300 MW. FEMA rates local natural-hazard risk as "Relatively Low". The county has a datacenter tax incentive on record.

27
Candidate sites
57.7/100
Avg DC Readiness
2,300 MW
Catalogued capacity
theoretical aggregate
Relatively Low
Hazard rating
◆ Loading map…
≥ 7560–7540–60≤ 40
Top 25 in McLean

Site-selection context for McLean

Yesproperty_tax_exemption
Datacenter tax incentive
10.13¢/kWh
Commercial electricity
7.57¢/kWh
Industrial electricity
4
Fiber providers
Low-Medium
Water stress
$2,556
Land price / acre
500
Cooling degree days
8,600
Heating degree days
40°F
Mean annual temp

Incentive detail: Property tax exemption for new DC construction for up to 5 years.

By site type

Top datacenter sites in McLean

Top datacenter sites in McLean
SiteTypeVoltageCapacityQueue waitScore
TAP134163Substation-Adjacent230 kV300 MW3.3 yrs62.9
UNKNOWN133143Substation-Adjacent230 kV300 MW3.3 yrs62.4
EC Near Coal CreekGreenfield1.4 yrs62.1
EC Near Coal CreekGreenfield1.4 yrs62.0
EC Near Coal CreekGreenfield1.4 yrs61.4
EC Near Coal CreekGreenfield1.4 yrs61.3
EC Near Coal CreekGreenfield1.4 yrs60.9
EC Near Coal CreekGreenfield1.4 yrs60.6
UNKNOWN158084Substation-Adjacent115 kV100 MW3.3 yrs58.8
EC Coal McLean CountyGreenfield1.4 yrs58.7
UNKNOWN134174Substation-Adjacent115 kV100 MW3.3 yrs58.1
UNKNOWN133965Substation-Adjacent115 kV100 MW3.3 yrs58.0
TAP133973Substation-Adjacent115 kV100 MW3.3 yrs58.0
TAP133969Substation-Adjacent115 kV100 MW3.3 yrs58.0
EC Coal McLean CountyGreenfield1.4 yrs57.8
UNKNOWN133974Substation-Adjacent115 kV100 MW3.3 yrs57.6
UNKNOWN133962Substation-Adjacent115 kV100 MW3.3 yrs57.5
UNKNOWN133975Substation-Adjacent115 kV100 MW3.3 yrs57.4
UNKNOWN133963Substation-Adjacent115 kV100 MW3.3 yrs56.7
Greenfield (UNKNOWN133143 - UNKNOWN135302)Greenfield230 kV300 MW3.3 yrs56.2
Greenfield (MCHENRY - TAP134163)Greenfield230 kV300 MW3.3 yrs56.0
Wilton Motors BuildingIndustrial3.3 yrs54.7
Mercer School BuildingIndustrial3.3 yrs52.7
Mine SiteFormer Mine3.3 yrs52.4
Mine SiteFormer Mine3.3 yrs52.4

McLean datacenter FAQ

How many datacenter sites are in McLean?
27 scored datacenter candidate sites, averaging 57.7/100 DC Readiness.
Does McLean offer datacenter tax incentives?
Property tax exemption for new DC construction for up to 5 years.
What is the natural-hazard risk in McLean?
FEMA's National Risk Index rates McLean as "Relatively Low" (score 20).
What are industrial electricity rates in McLean?
Average industrial electricity is 7.57¢/kWh and commercial is 10.13¢/kWh in McLean.

Dataset updated . Screening estimates derived from public data sources.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for McLean, North Dakota. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.