Skip to content
Gridcensus

Datacenter Sites in McLean, North Dakota

McLean has 27 scored datacenter candidate sites averaging 57.0/100 DC Readiness, with a catalogued aggregate of 2,300 MW. FEMA rates local natural-hazard risk as "Relatively Low". The county has a datacenter tax incentive on record.

At a glance

McLean, North Dakota has 27 scored datacenter candidate sites averaging 57.0/100 DC Readiness, roughly in line with the North Dakota average of 55.7. It ranks 12th of 43 North Dakota counties by number of sites and 11th by average score. The top-scoring site is Substation-Adjacent site · 5ddf9c33 at 62.9/100.

27
Candidate sites
57.0/100
Avg DC Readiness
2,300 MW
Catalogued capacity
theoretical aggregate
Relatively Low
Hazard rating
◆ Loading map…
≥ 7560–7540–60≤ 40
Top 25 in McLean

Site-selection context for McLean

Yesproperty_tax_exemption
Datacenter tax incentive
10.13¢/kWh
Commercial electricity
7.57¢/kWh
Industrial electricity
4
Fiber providers
Low-Medium
Water stress
$2,556
Land price / acre
500
Cooling degree days
8,600
Heating degree days
40°F
Mean annual temp

Incentive detail: Property tax exemption for new DC construction for up to 5 years.

How does McLean compare with other counties in North Dakota?

By number of scored sites, McLean ranks 12th of the 43 North Dakota counties with a county page, holding 2.6% of the state's 1,020 sites. Its average DC Readiness of 57.0/100 ranks 11th in the state and is roughly in line with the national average of 53.0. Nationally it has the 1383rd-largest site inventory of 2,964 counties with five or more sites. 0 sites score 70 or higher and 21 score 55 or higher.

What types of datacenter sites are in McLean?

Greenfield sites are the most common (12, 44% of the county's inventory), followed by substation-adjacent (11) and industrial (2). Site type reflects how the parcel was identified — next to a substation, on a former mine or brownfield, on industrial or federal excess land — and is scored on the same 14 factors either way.

What are power cost, hazard, water and fiber conditions in McLean?

Industrial electricity averages 7.57¢/kWh and commercial 10.13¢/kWh. FEMA's National Risk Index rates the county "Relatively Low" (20). WRI water stress is low-medium. 4 fiber providers report service in the county. The climate runs 500 cooling degree days a year with a mean temperature of 40°F. Land is valued around $2,556 an acre.

By site type

Top datacenter sites in McLean

Top datacenter sites in McLean
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN133143Substation-Adjacent230 kV300 MW4.3 yrs62.9
TAP134163Substation-Adjacent230 kV300 MW4.3 yrs62.5
EC Near Coal CreekGreenfield——4.3 yrs60.3
EC Near Coal CreekGreenfield——4.3 yrs60.2
EC Near Coal CreekGreenfield——4.3 yrs59.6
EC Near Coal CreekGreenfield——4.3 yrs59.5
EC Near Coal CreekGreenfield——4.3 yrs59.1
EC Near Coal CreekGreenfield——4.3 yrs58.8
UNKNOWN134174Substation-Adjacent115 kV100 MW4.3 yrs58.5
UNKNOWN158084Substation-Adjacent115 kV100 MW4.3 yrs58.5
TAP133969Substation-Adjacent115 kV100 MW4.3 yrs57.7
UNKNOWN133965Substation-Adjacent115 kV100 MW4.3 yrs57.7
TAP133973Substation-Adjacent115 kV100 MW4.3 yrs57.6
UNKNOWN133974Substation-Adjacent115 kV100 MW4.3 yrs57.2
UNKNOWN133962Substation-Adjacent115 kV100 MW4.3 yrs57.2
UNKNOWN133975Substation-Adjacent115 kV100 MW4.3 yrs57.1
EC Coal McLean CountyGreenfield——4.3 yrs56.9
UNKNOWN133963Substation-Adjacent115 kV100 MW4.3 yrs56.3
EC Coal McLean CountyGreenfield——4.3 yrs56.0
Greenfield (UNKNOWN133143 - UNKNOWN135302)Greenfield230 kV300 MW4.3 yrs55.9
Greenfield (MCHENRY - TAP134163)Greenfield230 kV300 MW4.3 yrs55.7
Wilton Motors BuildingIndustrial——4.3 yrs54.3
Mercer School BuildingIndustrial——4.3 yrs52.3
Mine SiteFormer Mine——4.3 yrs52.1
Mine SiteFormer Mine——4.3 yrs52.1

Every scored site in McLean

All 27 sites, best first.

McLean datacenter FAQ

How many datacenter sites are in McLean?

27 scored datacenter candidate sites, averaging 57.0/100 DC Readiness. That is the 12th-most of 43 North Dakota counties with five or more sites.

What is the highest-scoring datacenter site in McLean?

Substation-Adjacent site · 5ddf9c33 scores 62.9/100 DC Readiness, the highest of the 27 scored sites in McLean (a substation-adjacent site).

Does McLean offer datacenter tax incentives?

Property tax exemption for new DC construction for up to 5 years.

What is the natural-hazard risk in McLean?

FEMA's National Risk Index rates McLean as "Relatively Low" (score 20).

What are industrial electricity rates in McLean?

Average industrial electricity is 7.57¢/kWh and commercial is 10.13¢/kWh in McLean.

More in North Dakota

About this data

Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published November 12, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “Datacenter candidate sites in McLean, North Dakota”, https://gridcensus.com/datacenter-sites/north-dakota/mclean (data as of November 12, 2026).

Dataset updated . Screening estimates derived from public data sources.

Go deeper than the public screen

Every site and score for McLean, North Dakota is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.