Skip to content
Gridcensus

Datacenter Sites in Grand Forks, North Dakota

Grand Forks has 36 scored datacenter candidate sites averaging 59.4/100 DC Readiness, with a catalogued aggregate of 1,850 MW. FEMA rates local natural-hazard risk as "Relatively Low". The county has a datacenter tax incentive on record.

36
Candidate sites
59.4/100
Avg DC Readiness
1,850 MW
Catalogued capacity
theoretical aggregate
Relatively Low
Hazard rating
◆ Loading map…
≥ 7560–7540–60≤ 40
Top 25 in Grand Forks

Site-selection context for Grand Forks

Yesproperty_tax_exemption
Datacenter tax incentive
4.92¢/kWh
Commercial electricity
7.84¢/kWh
Industrial electricity
9
Fiber providers
Low-Medium
Water stress
$3,568
Land price / acre
500
Cooling degree days
8,600
Heating degree days
40°F
Mean annual temp

Incentive detail: Property tax exemption for new DC construction for up to 5 years.

By site type

Top datacenter sites in Grand Forks

Top datacenter sites in Grand Forks
SiteTypeVoltageCapacityQueue waitScore
GRAND FORKSSubstation-Adjacent345 kV600 MW3.3 yrs69.8
OZ Grand ForksGreenfield1.4 yrs67.9
OZ Grand ForksGreenfield1.4 yrs67.9
UNKNOWN133738Substation-Adjacent230 kV300 MW3.3 yrs66.9
UNKNOWN130180Substation-Adjacent115 kV100 MW2.8 yrs62.2
UNKNOWN133998Substation-Adjacent69 kV50 MW3.3 yrs61.6
EC Near Grand ForksGreenfield1.4 yrs60.7
TAP171152Substation-Adjacent69 kV50 MW2.8 yrs60.4
UNKNOWN130179Substation-Adjacent69 kV50 MW2.8 yrs60.4
TAP155893Substation-Adjacent69 kV50 MW3.3 yrs60.3
UNKNOWN133735Substation-Adjacent115 kV100 MW3.3 yrs60.3
EC Near Grand ForksGreenfield1.4 yrs59.7
EC Near Grand ForksGreenfield1.4 yrs59.5
EC Near Grand ForksGreenfield1.4 yrs59.5
EC Near Grand ForksGreenfield1.4 yrs59.3
UNKNOWN130318Substation-Adjacent115 kV100 MW2.8 yrs59.2
EC Near Grand ForksGreenfield1.4 yrs59.2
UNKNOWN130319Substation-Adjacent115 kV100 MW2.8 yrs59.2
EC Near Grand ForksGreenfield1.4 yrs58.2
EC Near Grand ForksGreenfield1.4 yrs58.2
EC Near Grand ForksGreenfield1.4 yrs57.9
EC Near Grand ForksGreenfield1.4 yrs57.8
TAP134016Substation-Adjacent69 kV50 MW3.3 yrs57.8
UNKNOWN134021Substation-Adjacent69 kV50 MW3.3 yrs57.7
UNKNOWN134601Substation-Adjacent69 kV50 MW3.3 yrs57.7

Grand Forks datacenter FAQ

How many datacenter sites are in Grand Forks?
36 scored datacenter candidate sites, averaging 59.4/100 DC Readiness.
Does Grand Forks offer datacenter tax incentives?
Property tax exemption for new DC construction for up to 5 years.
What is the natural-hazard risk in Grand Forks?
FEMA's National Risk Index rates Grand Forks as "Relatively Low" (score 20).
What are industrial electricity rates in Grand Forks?
Average industrial electricity is 7.84¢/kWh and commercial is 4.92¢/kWh in Grand Forks.

Dataset updated . Screening estimates derived from public data sources.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Grand Forks, North Dakota. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.