Skip to content
Gridcensus

Bowline Point

Brownfield

Rockland, New York · NYISO

DC Readiness
69.1
Good / 100

Bowline Point is a brownfield datacenter candidate site in Rockland, New York, interconnecting through NYISO. It screens at 69.1/100 DC Readiness with a catalogued 750 MW of candidate capacity and a 4.9 yrs average interconnection-queue wait.

Power & interconnection

Substation distance0.1 mi
Available capacity750 MW

Speed to power

ISO / RTO regionNYISO
Queue depth298
Avg queue wait4.9 yrs

Connectivity

Nearest IXPEvocative New York (JFK2)
IXP distance11.2 mi
Fiber providers8
Fiber coverage99.9%

Site characteristics

Site typeBrownfield
Former usegas
Existing capacity750 MW

Risk & environment

Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score65/100

Location context

Nearest datacenterDatacenter 1092283612
DC distance10.5 mi
County hazard (FEMA NRI)Relatively High (35)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.67¢/kWh
Industrial electricity6.84¢/kWh
Cooling degree days700
Heating degree days6,100
Land price / acre$13,052

Incentive detail: Excelsior Jobs Program tax credits; IDA property tax abatements (PILOT); Empire State Digital Gaming.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
75
Speed to power15%
63
Fiber connectivity12%
80
Energy cost10%
50
Water risk8%
90
Natural hazard8%
65
Buildability7%
75
Labor market4%
50
DC cluster4%
80
Land / acreage3%
57
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
90

Nearby comparable sites

Other scored datacenter candidate sites in Rockland, ranked by DC Readiness.

Sites near Bowline Point
SiteTypeVoltageCapacityQueue waitScore
RAMAPOSubstation-Adjacent500 kV1,000 MW4.9 yrs68.9
UNKNOWN132256Substation-Adjacent345 kV600 MW3.8 yrs66.9
LADENTOWNSubstation-Adjacent345 kV600 MW4.9 yrs66.5
W. HAVERSTRAWSubstation-Adjacent345 kV600 MW4.9 yrs66.5
BUCHANANSubstation-Adjacent345 kV600 MW4.9 yrs66.4
EC Near Bowline PointGreenfield3.5 yrs60.8
UNKNOWN129180Substation-Adjacent138 kV100 MW4.9 yrs60.7
EC Near Bowline PointGreenfield3.5 yrs60.6

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Bowline Point, Rockland. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.