Skip to content
Gridcensus

UNKNOWN129180

Substation-Adjacent

Rockland, New York · NYISO

DC Readiness
60.7
Good / 100

UNKNOWN129180 is a substation-adjacent datacenter candidate site in Rockland, New York, interconnecting through NYISO. It screens at 60.7/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 4.9 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN129180
Substation distance0.0 mi
Substation voltage138 kV
Available capacity100 MW

Speed to power

ISO / RTO regionNYISO
Queue depth298
Avg queue wait4.9 yrs

Connectivity

Nearest IXPDatabank Orangeburg (LGA3)
IXP distance10.9 mi
Fiber providers8
Fiber coverage99.9%

Site characteristics

Risk & environment

Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score65/100

Location context

Nearest datacenterNYSE Data Center
DC distance3.4 mi
County hazard (FEMA NRI)Relatively High (35)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.67¢/kWh
Industrial electricity6.84¢/kWh
Cooling degree days700
Heating degree days6,100
Land price / acre$13,052

Incentive detail: Excelsior Jobs Program tax credits; IDA property tax abatements (PILOT); Empire State Digital Gaming.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
58
Speed to power15%
38
Fiber connectivity12%
81
Energy cost10%
50
Water risk8%
90
Natural hazard8%
65
Buildability7%
60
Labor market4%
50
DC cluster4%
80
Land / acreage3%
48
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
90

Nearby comparable sites

Other scored datacenter candidate sites in Rockland, ranked by DC Readiness.

Sites near UNKNOWN129180
SiteTypeVoltageCapacityQueue waitScore
Bowline PointBrownfield750 MW4.9 yrs69.1
RAMAPOSubstation-Adjacent500 kV1,000 MW4.9 yrs68.9
UNKNOWN132256Substation-Adjacent345 kV600 MW3.8 yrs66.9
W. HAVERSTRAWSubstation-Adjacent345 kV600 MW4.9 yrs66.5
LADENTOWNSubstation-Adjacent345 kV600 MW4.9 yrs66.5
BUCHANANSubstation-Adjacent345 kV600 MW4.9 yrs66.4
EC Near Bowline PointGreenfield3.5 yrs60.8
EC Near Bowline PointGreenfield3.5 yrs60.6

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for UNKNOWN129180, Rockland. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.