Former Mine site at 42.122, -77.948

Former Mine

Allegany, New York · NYISO

DC Readiness
48.1
Fair / 100

At a glance

Former Mine site at 42.122, -77.948 is a former mine datacenter candidate site in Allegany, New York, scoring 48.1/100 DC Readiness — 37th of 39 scored sites in the county. It sits in the NYISO grid region and the NIAGARA MOHAWK POWER CORP. service territory, where interconnection has averaged 4.3 years from request to operation.

Power & interconnection

UtilityNIAGARA MOHAWK POWER CORP.investor ownedmoderate to large load · terms ≥ 20 MW

Speed to power

Interconnection outlookConstrained
≈ 4.9 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionNYISO
Queue depth95
Avg queue wait4.3 yrs
Recent queue wait4.9 yrs
Completion rate8%
Withdrawal rate92%

Connectivity

Nearest IXPVictory Technology Center
IXP distance66.0 mi
Fiber providers5
Fiber coverage71.3%

Site characteristics

Site typeFormer Mine
Former useMining: SandAndGravel; Status: Abandoned
Cleanup statusAbandoned

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score65/100

Location context

Nearest datacenterLandmax Data Systems, Inc
DC distance62.4 mi
County hazard (FEMA NRI)Relatively High (35)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity9.31¢/kWh
Industrial electricity6.68¢/kWh
Cooling degree days700
Heating degree days6,100
Land price / acre$3,316

Regulatory climate

Restrictivestate posture · as of 2026-08

First statewide moratorium (2026): 1-yr hold on certain permits for large DCs + impact study.

DC tax incentiveNo / suspended
Large-load threshold≥ 50 MW

Moratorium/permit hold targets large datacenters.

Incentive detail: Excelsior Jobs Program tax credits; IDA property tax abatements (PILOT); Empire State Digital Gaming.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Mine Site

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

How does Former Mine site at 42.122, -77.948 compare with other sites in Allegany?

Former Mine site at 42.122, -77.948 ranks 37th of 39 scored candidate sites in Allegany. Its 48.1/100 is roughly in line with the county average of 51.7. It is about 11% below the New York average of 54.0 and roughly in line with the national average of 53.2.

Against the New York average, its strongest sub-score is natural hazard (65 vs 64) and its weakest is fiber connectivity (65 vs 76). Power and speed to power each carry 20% of the composite score, fiber 12%, water 7% and hazard 6%.

How close is Former Mine site at 42.122, -77.948 to power, fiber and other datacenters?

The nearest located transmission bottleneck is MEYER 230 MEYER 1 1 (NYISO), 32 miles away. For connectivity, the nearest internet exchange facility is Victory Technology Center at 66 miles. 5 fiber providers report service at the location in FCC broadband data. The closest operating datacenter on record is Landmax Data Systems, Inc, 62.4 miles away.

What are the flood, water and hazard risks at Former Mine site at 42.122, -77.948?

At the county level, FEMA's National Risk Index rates Allegany "Relatively High".

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
39
Fiber connectivity12%
65
Energy cost10%
50
Water risk7%
90
Natural hazard6%
65
Buildability7%
50
Labor market4%
50
DC cluster4%
20
Land / acreage3%
48
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
90

Nearby comparable sites

Other scored datacenter candidate sites in Allegany, ranked by DC Readiness.

Sites near Former Mine site at 42.122, -77.948
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN124588Substation-Adjacent115 kV100 MW4.3 yrs55.5
UNKNOWN124581Substation-Adjacent115 kV100 MW4.3 yrs55.4
UNKNOWN124587Substation-Adjacent115 kV100 MW4.3 yrs55.4
EC Near Hyland LFGTE FacilityGreenfield——4.3 yrs55.2
EC Near Hyland LFGTE FacilityGreenfield——4.3 yrs55.1
UNKNOWN124589Substation-Adjacent115 kV100 MW4.3 yrs54.6
TAP140650Substation-Adjacent115 kV100 MW4.3 yrs54.6
Hyland LFGTE FacilityBrownfield—2 MW4.3 yrs54.5

Former Mine site at 42.122, -77.948: common questions

What is the DC Readiness score of Former Mine site at 42.122, -77.948?

Former Mine site at 42.122, -77.948 scores 48.1/100 on the GridCensus DC Readiness scale, rated fair. It ranks 37th of 39 scored sites in Allegany. The Allegany average is 51.7 and the New York average is 54.0.

Which electric utility serves Former Mine site at 42.122, -77.948?

NIAGARA MOHAWK POWER CORP. (investor owned) holds the retail service territory that contains the site; its holding company is NATIONAL GRID GROUP PLC.

What grid region is Former Mine site at 42.122, -77.948 in?

Former Mine site at 42.122, -77.948 is in the NYISO region. Projects interconnecting there have averaged a 4.3-year wait from queue request to operation.

How far is Former Mine site at 42.122, -77.948 from an internet exchange?

The nearest internet exchange facility is Victory Technology Center, about 66 miles away; 5 fiber providers report service at the location.

Related pages

About this data

Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published October 10, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “Former Mine site at 42.122, -77.948, Allegany, NY”, https://gridcensus.com/datacenter-sites/new-york/allegany/mine-site-8e224387 (data as of October 10, 2026).

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for Former Mine site at 42.122, -77.948, Allegany is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.