Skip to content
Gridcensus

Greenfield (BLACKSTONE JUNCTION - UNKNOWN1)

Greenfield

Bristol County, Massachusetts · ISO-NE

DC Readiness
49.5
Fair / 100

Greenfield (BLACKSTONE JUNCTION - UNKNOWN1) is a greenfield datacenter candidate site in Bristol County, Massachusetts, interconnecting through ISO-NE. It screens at 49.5/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.9 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationBLACKSTONE JUNCTION
Substation voltage115 kV
Available capacity100 MW
UtilityTOWN OF NORTH ATTLEBOROUGH - (MA)municipal

Speed to power

Interconnection outlookModerate
≈ 3.9 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionISO-NE
Queue depth25
Avg queue wait3.9 yrs

Connectivity

Nearest IXPCrown Castle Providence (235 Promenade)
IXP distance8.4 mi
Fiber providers3
Fiber coverage10.0%

Site characteristics

Site typeGreenfield

Risk & environment

Environmental constraintNone (0/100)
Flood zoneZone X
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score82/100

Location context

Nearest datacenterCrown Castle Providence (235 Promenade)
DC distance8.4 mi
County hazard (FEMA NRI)Relatively Low (18)
DC tax incentiveNo
Commercial electricity16.92¢/kWh
Industrial electricity18.04¢/kWh
Cooling degree days600
Heating degree days5,600
Land price / acre$49,530

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Greenfield (BLACKSTONE JUNCTION - UNKNOWN1)

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
28
Speed to power20%
37
Fiber connectivity12%
68
Energy cost10%
50
Water risk7%
90
Natural hazard6%
82
Buildability7%
50
Labor market4%
50
DC cluster4%
80
Land / acreage3%
30
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
0
Climate / cooling1%
95

Nearby comparable sites

Other scored datacenter candidate sites in Bristol County, ranked by DC Readiness.

Sites near Greenfield (BLACKSTONE JUNCTION - UNKNOWN1)
SiteTypeVoltageCapacityQueue waitScore
FALL RIVERSubstation-Adjacent345 kV600 MW3.9 yrs61.8
TAP136643Substation-Adjacent115 kV100 MW3.9 yrs57.8
WAMPANOUGSubstation-Adjacent115 kV100 MW3.9 yrs57.7
TAP140908Substation-Adjacent115 kV100 MW3.9 yrs57.6
UNKNOWN130684Substation-Adjacent115 kV100 MW3.9 yrs57.5
TAP140933Substation-Adjacent115 kV100 MW3.9 yrs56.5
BLACKSTONE JUNCTIONSubstation-Adjacent115 kV100 MW3.9 yrs56.5
TAP136638Substation-Adjacent115 kV100 MW3.9 yrs56.4

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.