EC Near Chanute 1

Greenfield

Neosho, Kansas · SPP

DC Readiness
54.7
Fair / 100

EC Near Chanute 1 is a greenfield datacenter candidate site in Neosho, Kansas, interconnecting through SPP. It screens at 54.7/100 DC Readiness and a 3.5 yrs average interconnection-queue wait.

Power & interconnection

LMP zoneSPP_NORTH
Wholesale LMP$21.13/MWh
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionSPP
Queue depth16
Avg queue wait3.5 yrs
Recent queue wait3.5 yrs
Completion rate16%
Withdrawal rate84%

Connectivity

Nearest IXPDataBank Kansas City (MCI3)
IXP distance96.4 mi
Fiber providers4
Fiber coverage68.9%
Nearest cloud providerGCP
Nearest cloud regionus-central1
Cloud region distance251.3 mi

Site characteristics

Site typeGreenfield
Parcel ownerKANSAS GAS & ELECTRIC CO
Land owner typeprivate
Buildability45.0/100
Land cover (NLCD)Deciduous Forest
Former usenear retired gas plant (5km)

Risk & environment

Flood zoneZone X
Water stress (WRI)2.40
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteT R DISPLAYS INC
Hazard sub-score55/100
Construction cost index89.0 (avg 100)

Location context

Nearest datacenterGoogle Pryor
DC distance92.2 mi
Nearest rail1.0 mi
Nearest gas pipeline0.8 mi
Nearest fiber route1.4 mi
County hazard (FEMA NRI)Relatively High (35)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity11.19¢/kWh
Industrial electricity8.43¢/kWh
Cooling degree days1,400
Heating degree days5,000
Land price / acre$2,282

Incentive detail: PEAK program payroll tax incentives; IRB property tax exemptions available.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
51
Fiber connectivity12%
68
Energy cost10%
90
Water risk8%
52
Natural hazard8%
55
Buildability7%
45
Labor market4%
50
DC cluster4%
20
Land / acreage3%
67
Construction cost3%
76
Gas pipeline2%
98
Tax incentive2%
100
Climate / cooling2%
55

Nearby comparable sites

Other scored datacenter candidate sites in Neosho, ranked by DC Readiness.

Sites near EC Near Chanute 1
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN118255Substation-Adjacent138 kV100 MW3.5 yrs63.7
Greenfield (NEOSHO - UNKNOWN173422)Greenfield345 kV600 MW3.5 yrs63.3
Greenfield (NEOSHO - UNKNOWN173422)Greenfield345 kV600 MW3.5 yrs62.8
UNKNOWN118256Substation-Adjacent138 kV100 MW3.5 yrs62.8
Greenfield (NEOSHO - UNKNOWN173422)Greenfield345 kV600 MW3.5 yrs61.6
Greenfield (UNKNOWN118255 - UNKNOWN118256)Greenfield138 kV100 MW3.5 yrs58.3
EC Near Chanute 1Greenfield3.5 yrs58.2
EC Coal Neosho CountyGreenfield3.5 yrs58.1

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for EC Near Chanute 1, Neosho. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.