Skip to content
Gridcensus

Greenfield (MIDWAY - BOONE)

Greenfield

Pueblo County, California · WECC

DC Readiness
51.6
Fair / 100

At a glance

Greenfield (MIDWAY - BOONE) is a greenfield datacenter candidate site in Pueblo County, California, scoring 51.6/100 DC Readiness — 62nd of 148 scored sites in the county. Its nearest substation is MIDWAY. It sits in the WECC grid region, where interconnection has averaged 7.6 years from request to operation. GridCensus catalogs 300 MW of candidate capacity here.

Power & interconnection

Nearest substationMIDWAY
Substation voltage230 kV
Available capacity300 MW

Speed to power

Interconnection outlookConstrained
≈ 8.3 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionWECC
Queue depth227
Avg queue wait7.6 yrs
Recent queue wait8.3 yrs
Completion rate11%
Withdrawal rate89%

Connectivity

Nearest IXPT5@Colorado Springs
IXP distance38.8 mi
Fiber providers8
Fiber coverage66.7%

Site characteristics

Site typeGreenfield

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score75/100

Location context

Nearest datacenterDatacenter 00476609221
DC distance30.5 mi
County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity13.62¢/kWh
Industrial electricity9.08¢/kWh
Cooling degree days700
Heating degree days6,200
Land price / acre$1,659

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Enterprise Zone sales tax exemptions; broadband equipment tax credit.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Greenfield (MIDWAY - BOONE)

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

How does Greenfield (MIDWAY - BOONE) compare with other sites in Pueblo County?

Greenfield (MIDWAY - BOONE) ranks 62nd of 148 scored candidate sites in Pueblo County. Its 51.6/100 is roughly in line with the county average of 52.0. It is about 14% above the California average of 45.4 and roughly in line with the national average of 53.2.

Against the California average, its strongest sub-score is natural hazard (75 vs 51) and its weakest is speed to power (42 vs 43). Power and speed to power each carry 20% of the composite score, fiber 12%, water 7% and hazard 6%.

How close is Greenfield (MIDWAY - BOONE) to power, fiber and other datacenters?

The nearest mapped substation, MIDWAY, is the closest grid connection point on record and operates at 230 kV. For connectivity, the nearest internet exchange facility is T5@Colorado Springs at 38.8 miles. 8 fiber providers report service at the location in FCC broadband data. The closest operating datacenter on record is Datacenter 00476609221, 30.5 miles away.

What are the flood, water and hazard risks at Greenfield (MIDWAY - BOONE)?

At the county level, FEMA's National Risk Index rates Pueblo County "Relatively Moderate".

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
50
Speed to power20%
42
Fiber connectivity12%
67
Energy cost10%
50
Water risk7%
36
Natural hazard6%
75
Buildability7%
50
Labor market4%
50
DC cluster4%
60
Land / acreage3%
52
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
90

Nearby comparable sites

Other scored datacenter candidate sites in Pueblo County, ranked by DC Readiness.

Sites near Greenfield (MIDWAY - BOONE)
SiteTypeVoltageCapacityQueue waitScore
COMANCHESubstation-Adjacent345 kV600 MW3.5 yrs63.8
PUEBLOSubstation-Adjacent230 kV300 MW3.5 yrs59.1
EC Near Pueblo Airport Generating StationGreenfield——3.5 yrs58.8
BOONESubstation-Adjacent230 kV300 MW3.5 yrs58.8
OZ PuebloGreenfield——3.5 yrs58.6
EC Near Pueblo Airport Generating StationGreenfield——3.5 yrs58.5
EC Near Pueblo Airport Generating StationGreenfield——3.5 yrs58.1
EC Coal Pueblo CountyGreenfield——4.3 yrs58.0

Greenfield (MIDWAY - BOONE): common questions

What is the DC Readiness score of Greenfield (MIDWAY - BOONE)?

Greenfield (MIDWAY - BOONE) scores 51.6/100 on the GridCensus DC Readiness scale, rated fair. It ranks 62nd of 148 scored sites in Pueblo County. The Pueblo County average is 52.0 and the California average is 45.4.

What is the nearest substation to Greenfield (MIDWAY - BOONE)?

The nearest mapped substation is MIDWAY, at 230 kV. GridCensus catalogs 300 MW of candidate capacity for the site.

What grid region is Greenfield (MIDWAY - BOONE) in?

Greenfield (MIDWAY - BOONE) is in the WECC region. Projects interconnecting there have averaged a 7.6-year wait from queue request to operation.

How far is Greenfield (MIDWAY - BOONE) from an internet exchange?

The nearest internet exchange facility is T5@Colorado Springs, about 38.8 miles away; 8 fiber providers report service at the location.

Related pages

About this data

Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published October 10, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “Greenfield (MIDWAY - BOONE), Pueblo County, CA”, https://gridcensus.com/datacenter-sites/california/pueblo-county/greenfield-midway-boone-a079183f (data as of October 10, 2026).

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for Greenfield (MIDWAY - BOONE), Pueblo County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.