Datacenter Sites in Limestone County, Alabama
Limestone County has 24 scored datacenter candidate sites averaging 62.1/100 DC Readiness, with a catalogued aggregate of 5,100 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
24
Candidate sites
62.1/100
Avg DC Readiness
5,100 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Limestone County
Yessales_tax_exemption
Datacenter tax incentive
10.34¢/kWh
Commercial electricity
5.97¢/kWh
Industrial electricity
9
Fiber providers
Low
Water stress
$4,683
Land price / acre
2,100
Cooling degree days
2,800
Heating degree days
63°F
Mean annual temp
Incentive detail: Sales & use tax abatement on qualifying equipment. $400M+ investment threshold.
By site type
Top datacenter sites in Limestone County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| LIMESTONE | Substation-Adjacent | 500 kV | 1,000 MW | 1.0 yrs | 72.3 |
| TRINITY | Substation-Adjacent | 500 kV | 1,000 MW | 1.0 yrs | 70.8 |
| UNKNOWN114484 | Substation-Adjacent | 500 kV | 1,000 MW | 1.0 yrs | 70.7 |
| BROWNS FERRY | Substation-Adjacent | 500 kV | 1,000 MW | 1.0 yrs | 70.2 |
| UNKNOWN111049 | Substation-Adjacent | 161 kV | 100 MW | 1.0 yrs | 64.3 |
| PEACH ORCHARD | Substation-Adjacent | 161 kV | 100 MW | 1.0 yrs | 64.2 |
| ARDMORE | Substation-Adjacent | 161 kV | 100 MW | 1.0 yrs | 63.4 |
| GM | Substation-Adjacent | 161 kV | 100 MW | 1.0 yrs | 63.4 |
| ATHENS | Substation-Adjacent | 161 kV | 100 MW | 1.0 yrs | 63.3 |
| UNKNOWN114488 | Substation-Adjacent | 161 kV | 100 MW | 1.0 yrs | 63.0 |
| UNKNOWN114485 | Substation-Adjacent | 161 kV | 100 MW | 1.0 yrs | 62.8 |
| UNKNOWN114550 | Substation-Adjacent | 161 kV | 100 MW | 1.0 yrs | 62.8 |
| TAP155269 | Substation-Adjacent | 161 kV | 100 MW | 1.0 yrs | 62.7 |
| OZ Limestone | Greenfield | — | — | 3.7 yrs | 61.9 |
| OZ Limestone | Greenfield | — | — | 3.7 yrs | 60.8 |
| ROGERSVILLE | Substation-Adjacent | 161 kV | 100 MW | 1.0 yrs | 60.5 |
| Greenfield (NORTHWEST PRIMARY - TAP176124) | Greenfield | 161 kV | 100 MW | 1.0 yrs | 57.9 |
| Mine Site | Former Mine | — | — | 1.0 yrs | 57.5 |
| DECATUR AL | Federal Excess | — | — | 1.0 yrs | 57.5 |
| Mine Site | Former Mine | — | — | 1.0 yrs | 57.5 |
| Pilgrim's Pride | Industrial | — | — | 1.0 yrs | 56.6 |
| Pilgrim's Pride/Sweet Sue facilities | Industrial | — | — | 1.0 yrs | 56.6 |
| Mine Site | Former Mine | — | — | 1.0 yrs | 55.1 |
| Mine Site | Former Mine | — | — | 1.0 yrs | 54.0 |
Limestone County datacenter FAQ
- How many datacenter sites are in Limestone County?
- 24 scored datacenter candidate sites, averaging 62.1/100 DC Readiness.
- Does Limestone County offer datacenter tax incentives?
- Sales & use tax abatement on qualifying equipment. $400M+ investment threshold.
- What is the natural-hazard risk in Limestone County?
- FEMA's National Risk Index rates Limestone County as "Relatively High" (score 45).
- What are industrial electricity rates in Limestone County?
- Average industrial electricity is 5.97¢/kWh and commercial is 10.34¢/kWh in Limestone County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Limestone County, Alabama. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.