At a glance
GOSHEN is an electric transmission substation in Virginia, on VIRGINIA ELECTRIC & POWER CO's transmission network. It is classified as sub-transmission (115 kv) and connects 4 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.
Voltage & classification
Ownership
Connected transmission lines
Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.
| Line ID | Voltage | Owner | Status | Length |
|---|---|---|---|---|
| #111206 | 115 kV | VIRGINIA ELECTRIC & POWER CO | IN SERVICE | 29.2 mi |
| #127058 | 115 kV | VIRGINIA ELECTRIC & POWER CO | IN SERVICE | 10.4 mi |
| #150197 | — | VIRGINIA ELECTRIC & POWER CO | IN SERVICE | 10.9 mi |
| #174071 | — | VIRGINIA ELECTRIC & POWER CO | IN SERVICE | 8.2 mi |
Nearby datacenter candidate sites
Scored candidate sites within roughly 25 miles of GOSHEN, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.
| Site | Type | State | County | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|---|---|
| LEXINGTON | Substation-Adjacent | VA | Rockbridge County | 500 kV | 1,000 MW | 5.1 yrs | 64.8 |
| BATH COUNTY | Substation-Adjacent | VA | Bath County | 500 kV | 1,000 MW | 5.1 yrs | 64.5 |
| CLIFTON FORGE | Substation-Adjacent | VA | Covington city | 230 kV | 300 MW | 5.1 yrs | 61.4 |
| LOWMOOR | Substation-Adjacent | VA | Covington city | 230 kV | 300 MW | 5.1 yrs | 61.3 |
| WEST STAUNTON | Substation-Adjacent | VA | Augusta County | 230 kV | 300 MW | 5.1 yrs | 60.7 |
| BUENA VISTA | Substation-Adjacent | VA | Buena Vista city | 115 kV | 100 MW | 5.1 yrs | 57.8 |
| CUSHAW | Substation-Adjacent | VA | Buena Vista city | 115 kV | 100 MW | 5.1 yrs | 57.8 |
| GLASGOW | Substation-Adjacent | VA | Buena Vista city | 115 kV | 100 MW | 5.1 yrs | 57.8 |
How does GOSHEN compare with other substations in Virginia?
Virginia has 1,382 substation records in HIFLD, of which 529 carry a station name; the rest are unnamed tap points, risers and line ends. 238 named substations in the state are in GOSHEN's 115–229 kV band (45% of named stations). 212 sit in a higher band. 39 named substations in Virginia operate at 345 kV or above. The highest voltage recorded in the state is 765 kV, and the state median is 138 kV.
Who owns the transmission lines at GOSHEN?
The 4 connected lines listed above are owned by VIRGINIA ELECTRIC & POWER CO. Line voltages range from 115 kV to 115 kV. Their combined recorded length is about 58.8 miles.
How do candidate sites near GOSHEN score?
The 8 highest-scoring candidate sites within about 25 miles range from 58 to 65 on the 0–100 DC Readiness scale. They fall in Rockbridge County, Bath County, Covington city, Augusta County. The Virginia average across 5,871 scored sites is 52.6. 733 of those Virginia sites are classed as substation sites (candidate locations generated at an existing substation).
Frequently asked questions
What voltage is GOSHEN substation?
GOSHEN has a maximum voltage of 115 kV. That places it in the 115–229 kV band. The median named US substation in this dataset is 115 kV, so GOSHEN is at the national midpoint.
How many transmission lines connect to GOSHEN substation?
4 transmission lines terminate at or pass through GOSHEN in the HIFLD line data. The connected lines listed here run at 115 kV. Together the listed lines cover about 58.8 miles.
Who owns GOSHEN substation?
HIFLD does not publish substation owners directly. Most of the transmission lines that end at GOSHEN belong to VIRGINIA ELECTRIC & POWER CO. GridCensus derives this from the line data, so confirm ownership with the utility for anything contractual.
Where is GOSHEN substation located?
GOSHEN is in Virginia at 37.9683, -79.5092. The datacenter candidate sites closest to it are in Rockbridge County, Bath County, Covington city.
Are there datacenter candidate sites near GOSHEN substation?
GridCensus lists at least 8 scored candidate sites within roughly 25 miles of GOSHEN. The highest-scoring is LEXINGTON at 65/100. Across Virginia, the average DC Readiness score is 52.6.
Other 115 kV substations in Virginia
- CHASE CITY· 7 lines
- KERR DAM· 7 lines
- HARRISON· 6 lines
- ST JOHNS DP· 6 lines
- ACCA· 5 lines
- BALCONY FALLS· 5 lines
- DAVIS· 5 lines
- ST. JOHNS· 5 lines
- All named substations in Virginia· 529 stations
- Datacenter candidate sites in Virginia· 5,871 sites
- Brownfield and retired plant sites in Virginia
- Substations by state
About this data
Source: HIFLD Electric Substations and Transmission Lines (U.S. Department of Homeland Security), as published June 29, 2026. See the methodology for how records are matched, cleaned and scored.
Cite as: GridCensus, “GOSHEN substation, Virginia”, https://gridcensus.com/substations/virginia/goshen-25d0751e (data as of June 29, 2026).
Dataset updated . Screening estimates derived from public data sources.
Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.
Go deeper than the public screen
Every site and score for GOSHEN substation, Virginia is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.