At a glance

TAP307850 is a 66 kV electric substation in California on SOUTHERN CALIFORNIA EDISON's transmission network, recorded in the HIFLD transmission dataset. 3 transmission lines connect to it. The highest-scoring datacenter candidate site within about 25 miles is STATION E (TOLUCA) in Los Angeles County, with a DC Readiness score of 63/100.

TAP307850 is an electric transmission substation in California, on SOUTHERN CALIFORNIA EDISON's transmission network. It is classified as distribution (<69 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage66 kV
Min voltage66 kV
Voltage classDistribution (<69 kV)
Connected lines3

Ownership

Line owner (most lines)SOUTHERN CALIFORNIA EDISON
Coordinates34.5651, -118.1402

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#31376866 kVSOUTHERN CALIFORNIA EDISONIN SERVICE5.7 mi
#31377566 kVSOUTHERN CALIFORNIA EDISONIN SERVICE1.1 mi
#31377766 kVSOUTHERN CALIFORNIA EDISONIN SERVICE2.9 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP307850, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP307850 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
STATION E (TOLUCA)Substation-AdjacentCALos Angeles County500 kV1,000 MW7.6 yrs62.6
STATION M(VALLEY)Substation-AdjacentCALos Angeles County230 kV300 MW7.6 yrs61.7
RINALDISubstation-AdjacentCALos Angeles County500 kV1,000 MW7.6 yrs60.9
VINCENTSubstation-AdjacentCALos Angeles County500 kV1,000 MW7.6 yrs59.8
MagnoliaBrownfieldCALos Angeles County66 kV88 MW7.6 yrs58.8
ANTELOPESubstation-AdjacentCALos Angeles County500 kV1,000 MW7.6 yrs58.5
UNKNOWN300537Substation-AdjacentCALos Angeles County345 kV600 MW7.6 yrs58.4
UNKNOWN310464Substation-AdjacentCALos Angeles County345 kV600 MW7.6 yrs58.3

Who owns the transmission lines at TAP307850?

The 3 connected lines listed above are owned by SOUTHERN CALIFORNIA EDISON. Line voltages range from 66 kV to 66 kV. Their combined recorded length is about 9.8 miles.

How do candidate sites near TAP307850 score?

The 8 highest-scoring candidate sites within about 25 miles range from 58 to 63 on the 0–100 DC Readiness scale. They fall in Los Angeles County. The California average across 8,490 scored sites is 45.4. 1,573 of those California sites are classed as substation sites (candidate locations generated at an existing substation).

Frequently asked questions

What voltage is TAP307850 substation?

TAP307850 has a maximum voltage of 66 kV. That places it in the below 69 kV band. The median named US substation in this dataset is 115 kV, so TAP307850 is below the national midpoint.

How many transmission lines connect to TAP307850 substation?

3 transmission lines terminate at or pass through TAP307850 in the HIFLD line data. The connected lines listed here run at 66 kV. Together the listed lines cover about 9.8 miles.

Who owns TAP307850 substation?

HIFLD does not publish substation owners directly. Most of the transmission lines that end at TAP307850 belong to SOUTHERN CALIFORNIA EDISON. GridCensus derives this from the line data, so confirm ownership with the utility for anything contractual.

Where is TAP307850 substation located?

TAP307850 is in California at 34.5651, -118.1402. The datacenter candidate sites closest to it are in Los Angeles County.

Are there datacenter candidate sites near TAP307850 substation?

GridCensus lists at least 8 scored candidate sites within roughly 25 miles of TAP307850. The highest-scoring is STATION E (TOLUCA) at 63/100. Across California, the average DC Readiness score is 45.4.

More in California

About this data

Source: HIFLD Electric Substations and Transmission Lines (U.S. Department of Homeland Security), as published June 29, 2026. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “TAP307850 substation, California”, https://gridcensus.com/substations/california/tap307850-1ec2e978 (data as of June 29, 2026).

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

Every site and score for TAP307850 substation, California is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.