At a glance

TAP302707 is a 60 kV electric substation in California on PACIFIC GAS & ELECTRIC COMPANY's transmission network, recorded in the HIFLD transmission dataset. 3 transmission lines connect to it. The highest-scoring datacenter candidate site within about 25 miles is TESLA Power Project in Alameda County, with a DC Readiness score of 67/100.

TAP302707 is an electric transmission substation in California, on PACIFIC GAS & ELECTRIC COMPANY's transmission network. It is classified as distribution (<69 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage60 kV
Min voltage60 kV
Voltage classDistribution (<69 kV)
Connected lines3

Ownership

Line owner (most lines)PACIFIC GAS & ELECTRIC COMPANY
Coordinates37.9609, -121.3334

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#30274460 kVPACIFIC GAS & ELECTRIC COMPANYIN SERVICE2.4 mi
#30297460 kVPACIFIC GAS & ELECTRIC COMPANYIN SERVICE0.4 mi
#31200760 kVPACIFIC GAS & ELECTRIC COMPANYIN SERVICE0.6 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP302707, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP302707 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
TESLA Power ProjectBrownfieldCAAlameda County500 kV1,322 MW7.6 yrs66.5
TESLASubstation-AdjacentCAAlameda County500 kV1,000 MW7.6 yrs59.2
TRACYSubstation-AdjacentCASan Joaquin County500 kV1,000 MW7.6 yrs58.6
COUNTRY CLUBSubstation-AdjacentCASan Joaquin County230 kV300 MW7.6 yrs57.6
PRESCOTTSubstation-AdjacentCAStanislaus County230 kV300 MW7.6 yrs57.1
ROSEMORE BSubstation-AdjacentCAStanislaus County230 kV300 MW7.6 yrs57.0
STAGGSubstation-AdjacentCASan Joaquin County230 kV300 MW7.6 yrs56.6
WEBERSubstation-AdjacentCASan Joaquin County230 kV300 MW7.6 yrs56.5

Who owns the transmission lines at TAP302707?

The 3 connected lines listed above are owned by PACIFIC GAS & ELECTRIC COMPANY. Line voltages range from 60 kV to 60 kV. Their combined recorded length is about 3.4 miles.

How do candidate sites near TAP302707 score?

The 8 highest-scoring candidate sites within about 25 miles range from 57 to 67 on the 0–100 DC Readiness scale. They fall in Alameda County, San Joaquin County, Stanislaus County. The California average across 8,490 scored sites is 45.4. 1,573 of those California sites are classed as substation sites (candidate locations generated at an existing substation).

Frequently asked questions

What voltage is TAP302707 substation?

TAP302707 has a maximum voltage of 60 kV. That places it in the below 69 kV band. The median named US substation in this dataset is 115 kV, so TAP302707 is below the national midpoint.

How many transmission lines connect to TAP302707 substation?

3 transmission lines terminate at or pass through TAP302707 in the HIFLD line data. The connected lines listed here run at 60 kV. Together the listed lines cover about 3.4 miles.

Who owns TAP302707 substation?

HIFLD does not publish substation owners directly. Most of the transmission lines that end at TAP302707 belong to PACIFIC GAS & ELECTRIC COMPANY. GridCensus derives this from the line data, so confirm ownership with the utility for anything contractual.

Where is TAP302707 substation located?

TAP302707 is in California at 37.9609, -121.3334. The datacenter candidate sites closest to it are in Alameda County, San Joaquin County, Stanislaus County.

Are there datacenter candidate sites near TAP302707 substation?

GridCensus lists at least 8 scored candidate sites within roughly 25 miles of TAP302707. The highest-scoring is TESLA Power Project at 67/100. Across California, the average DC Readiness score is 45.4.

More in California

About this data

Source: HIFLD Electric Substations and Transmission Lines (U.S. Department of Homeland Security), as published June 29, 2026. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “TAP302707 substation, California”, https://gridcensus.com/substations/california/tap302707-eea558cc (data as of June 29, 2026).

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

Every site and score for TAP302707 substation, California is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.