SEEDSKADEE

Federal Excess

Lincoln County, Wyoming · WECC

DC Readiness
38.2
Limited / 100

SEEDSKADEE is a federal excess datacenter candidate site in Lincoln County, Wyoming, interconnecting through WECC. It screens at 38.2/100 DC Readiness.

Power & interconnection

Speed to power

ISO / RTO regionWECC
Queue depth74

Connectivity

Nearest IXPACT Riverton
IXP distance109.0 mi

Site characteristics

Acreage237 ac
Former useReclamation and Irrigation

Risk & environment

Water stress (WRI)Medium-High
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score50/100

Location context

Nearest datacenterFamily History Center
DC distance66.6 mi
County hazard (FEMA NRI)Very Low (10)
DC tax incentiveYes (no_income_tax)
Commercial electricity8.43¢/kWh
Industrial electricity6.50¢/kWh
Cooling degree days300
Heating degree days7,600
Land price / acre$3,963

Incentive detail: No state corporate or personal income tax; low property taxes.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
25
Fiber connectivity12%
39
Energy cost10%
50
Water risk8%
50
Natural hazard8%
50
Buildability7%
50
Labor market4%
50
DC cluster4%
20
Land / acreage3%
58
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
0
Climate / cooling2%
50

Nearby comparable sites

Other scored datacenter candidate sites in Lincoln County, ranked by DC Readiness.

Sites near SEEDSKADEE
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN202402Substation-Adjacent230 kV300 MW1.7 yrs71.6
UNKNOWN202400Substation-Adjacent230 kV300 MW1.7 yrs70.6
CRAVEN CREEKSubstation-Adjacent230 kV300 MW1.7 yrs70.1
UNKNOWN201480Substation-Adjacent230 kV300 MW1.7 yrs68.8
UNKNOWN203660Substation-Adjacent230 kV300 MW1.7 yrs68.4
UNKNOWN202531Substation-Adjacent230 kV300 MW1.7 yrs67.1
Greenfield (POPULUS - JIM BRIDGER)Greenfield345 kV600 MW1.7 yrs64.6
Greenfield (POPULUS - JIM BRIDGER)Greenfield345 kV600 MW1.7 yrs64.5

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for SEEDSKADEE, Lincoln County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.