TOWER SUBSTATION

Substation-Adjacent

Sauk County, Wisconsin · MISO

DC Readiness
56.5
Good / 100

TOWER SUBSTATION is a substation-adjacent datacenter candidate site in Sauk County, Wisconsin, interconnecting through MISO. It screens at 56.5/100 DC Readiness with a catalogued 50 MW of candidate capacity and a 2.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTOWER SUBSTATION
Substation distance0.0 mi
Substation voltage69 kV
Available capacity50 MW

Speed to power

ISO / RTO regionMISO
Queue depth27
Avg queue wait2.8 yrs

Connectivity

Nearest IXPSupraNet Communications Madison
IXP distance18.8 mi
Fiber providers9
Fiber coverage67.8%

Site characteristics

Risk & environment

Flood zoneZone X
Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score78/100

Location context

Nearest datacenterSupraNet Communications Madison
DC distance18.8 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.55¢/kWh
Industrial electricity9.01¢/kWh
Cooling degree days600
Heating degree days7,200
Land price / acre$6,278

Incentive detail: Enterprise Zone tax credits; TIF available for DC construction in eligible areas.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
46
Speed to power15%
40
Fiber connectivity12%
58
Energy cost10%
50
Water risk8%
94
Natural hazard8%
78
Buildability7%
60
Labor market4%
50
DC cluster4%
60
Land / acreage3%
45
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
95

Nearby comparable sites

Other scored datacenter candidate sites in Sauk County, ranked by DC Readiness.

Sites near TOWER SUBSTATION
SiteTypeVoltageCapacityQueue waitScore
TAP162959Substation-Adjacent69 kV50 MW2.8 yrs58.2
FINNEGANSubstation-Adjacent138 kV100 MW2.8 yrs57.9
TAP138067Substation-Adjacent138 kV100 MW2.8 yrs57.7
KIRKWOODSubstation-Adjacent138 kV100 MW2.8 yrs57.3
WICK DRIVESubstation-Adjacent69 kV50 MW2.8 yrs57.2
LOCH MIRRORSubstation-Adjacent138 kV100 MW2.8 yrs57.1
DELL CREEKSubstation-Adjacent138 kV100 MW2.8 yrs57.1
BIRCHWOODSubstation-Adjacent138 kV100 MW2.8 yrs57.1

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TOWER SUBSTATION, Sauk County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.