Datacenter Sites in Sauk County, Wisconsin
Sauk County has 48 scored datacenter candidate sites averaging 50.5/100 DC Readiness, with a catalogued aggregate of 1,600 MW. FEMA rates local natural-hazard risk as "Relatively Low". The county has a datacenter tax incentive on record.
48
Candidate sites
50.5/100
Avg DC Readiness
1,600 MW
Catalogued capacity
theoretical aggregate
Relatively Low
Hazard rating
Site-selection context for Sauk County
Yessales_tax_exemption
Datacenter tax incentive
12.55¢/kWh
Commercial electricity
9.01¢/kWh
Industrial electricity
10
Fiber providers
Low
Water stress
$6,278
Land price / acre
600
Cooling degree days
7,200
Heating degree days
44°F
Mean annual temp
Incentive detail: Enterprise Zone tax credits; TIF available for DC construction in eligible areas.
By site type
Top datacenter sites in Sauk County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| FOX HILLS | Substation-Adjacent | 138 kV | 100 MW | 1.4 yrs | 71.9 |
| LOCH MIRROR | Substation-Adjacent | 138 kV | 100 MW | 1.4 yrs | 71.8 |
| ROCK SPRINGS | Substation-Adjacent | 138 kV | 100 MW | 1.4 yrs | 69.9 |
| FINNEGAN | Substation-Adjacent | 138 kV | 100 MW | 1.4 yrs | 68.5 |
| KIRKWOOD | Substation-Adjacent | 138 kV | 100 MW | 1.4 yrs | 68.4 |
| ZOBEL | Substation-Adjacent | 138 kV | 100 MW | 1.4 yrs | 68.3 |
| BIRCHWOOD | Substation-Adjacent | 138 kV | 100 MW | 1.4 yrs | 68.1 |
| REEDSBURG NISHAN | Substation-Adjacent | 138 kV | 100 MW | 1.4 yrs | 67.8 |
| TAP138011 | Substation-Adjacent | 138 kV | 100 MW | 1.4 yrs | 66.9 |
| TROY | Substation-Adjacent | 138 kV | 100 MW | 1.4 yrs | 66.2 |
| DELL CREEK | Substation-Adjacent | 138 kV | 100 MW | 1.4 yrs | 66.2 |
| TAP138012 | Substation-Adjacent | 138 kV | 100 MW | 1.4 yrs | 65.8 |
| TAP138011 | Substation-Adjacent | 138 kV | 100 MW | 1.4 yrs | 64.4 |
| ARTESIAN | Substation-Adjacent | 138 kV | 100 MW | 1.4 yrs | 63.5 |
| Greenfield (KIRKWOOD - TAP138067) | Greenfield | 138 kV | 100 MW | 1.4 yrs | 59.1 |
| Greenfield (KIRKWOOD - TAP138067) | Greenfield | 138 kV | 100 MW | 1.4 yrs | 57.1 |
| Forner Veolia Environmental Services Property | Industrial | — | — | — | 44.3 |
| Parcels 1926 & 0933 | Industrial | — | — | — | 44.3 |
| Vine Street Right-of-Way | Industrial | — | — | — | 44.3 |
| Former Alliant Sites | Industrial | — | — | — | 44.3 |
| Bear-A-Boo Day Care | Industrial | — | — | — | 44.3 |
| Western MFG Gas Plant | Industrial | — | — | — | 44.3 |
| Outlying Parcels Lot 1 and Lot 2 | Industrial | — | — | — | 44.3 |
| USDA DAIRY FORAGE RESEARCH CTR | Federal Excess | — | — | — | 44.2 |
| St. Mary's Ringling Manor | Industrial | — | — | — | 44.2 |
Sauk County datacenter FAQ
- How many datacenter sites are in Sauk County?
- 48 scored datacenter candidate sites, averaging 50.5/100 DC Readiness.
- Does Sauk County offer datacenter tax incentives?
- Enterprise Zone tax credits; TIF available for DC construction in eligible areas.
- What is the natural-hazard risk in Sauk County?
- FEMA's National Risk Index rates Sauk County as "Relatively Low" (score 22).
- What are industrial electricity rates in Sauk County?
- Average industrial electricity is 9.01¢/kWh and commercial is 12.55¢/kWh in Sauk County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Sauk County, Wisconsin. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.