WEBER BASIN

Federal Excess

Summit County, Utah · WECC

DC Readiness
50.3
Fair / 100

WEBER BASIN is a federal excess datacenter candidate site in Summit County, Utah, interconnecting through WECC. It screens at 50.3/100 DC Readiness and a 6.9 yrs average interconnection-queue wait.

Power & interconnection

Speed to power

Interconnection outlookConstrained
≈ 6.9 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionWECC
Queue depth34
Avg queue wait6.9 yrs

Connectivity

Nearest IXPFlexential - Salt Lake City/Cottonwood (SLC05)
IXP distance23.6 mi
Fiber providers11
Fiber coverage38.3%

Site characteristics

Acreage84 ac
Buildable load (est.)~34–84 MWland-based
Former useReclamation and Irrigation

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score85/100

Location context

Nearest datacenterFlexential - Salt Lake City/Cottonwood (SLC05)
DC distance23.6 mi
County hazard (FEMA NRI)Relatively Low (15)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity9.26¢/kWh
Industrial electricity8.30¢/kWh
Cooling degree days1,000
Heating degree days5,500
Land price / acre$4,336

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Enterprise Zone tax credits; Economic Development Tax Increment Financing (EDTIF).

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track WEBER BASIN

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
57
Fiber connectivity12%
66
Energy cost10%
50
Water risk7%
24
Natural hazard6%
85
Buildability7%
50
Labor market4%
50
DC cluster4%
60
Land / acreage3%
61
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
75

Nearby comparable sites

Other scored datacenter candidate sites in Summit County, ranked by DC Readiness.

Sites near WEBER BASIN
SiteTypeVoltageCapacityQueue waitScore
TAP208893Substation-Adjacent115 kV100 MW6.9 yrs55.7
TAP208897Substation-Adjacent115 kV100 MW6.9 yrs55.1
TAP204604Substation-Adjacent138 kV100 MW6.9 yrs54.3
UNKNOWN206818Substation-Adjacent115 kV100 MW6.9 yrs53.9
Mine SiteFormer Mine——6.9 yrs51.9
CUP, BONNEVILLE UNITFederal Excess——6.9 yrs51.0
Alice Lode MiningIndustrial——6.9 yrs50.8
WEBER BASINFederal Excess——6.9 yrs50.5

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.