EC Coal Garfield County

Greenfield

Garfield County, Utah · WECC

DC Readiness
53.5
Fair / 100

EC Coal Garfield County is a greenfield datacenter candidate site in Garfield County, Utah, interconnecting through WECC. It screens at 53.5/100 DC Readiness and a 1.7 yrs average interconnection-queue wait.

Power & interconnection

Utility commercial rate0.10¢/kWh

Speed to power

ISO / RTO regionWECC
Queue depth74
Avg queue wait1.7 yrs
Recent queue wait1.0 yrs
Completion rate17%
Withdrawal rate84%

Connectivity

Nearest IXPTonaquint Data Center - Saint George
IXP distance139.2 mi
Fiber providers2
Fiber coverage71.8%
Nearest cloud providerGCP
Nearest cloud regionus-west3
Cloud region distance203.1 mi

Site characteristics

Site typeGreenfield
Parcel ownerPACIFICORP
Land owner typeprivate
Buildability70.0/100
Land cover (NLCD)Shrub/Scrub
Former usecoal adjacent

Risk & environment

Flood zoneZone X
Water stress (WRI)3.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score85/100
Construction cost index73.9 (avg 100)

Location context

Nearest datacenterLumen
DC distance136.6 mi
Nearest rail2.4 mi
Nearest gas pipeline84.4 mi
Nearest fiber route84.2 mi
County hazard (FEMA NRI)Relatively Low (15)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.28¢/kWh
Industrial electricity7.05¢/kWh
Cooling degree days1,000
Heating degree days5,500
Land price / acre$4,398

Incentive detail: Enterprise Zone tax credits; Economic Development Tax Increment Financing (EDTIF).

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
34
Fiber connectivity12%
62
Energy cost10%
96
Water risk8%
40
Natural hazard8%
85
Buildability7%
70
Labor market4%
50
DC cluster4%
20
Land / acreage3%
48
Construction cost3%
88
Gas pipeline2%
0
Tax incentive2%
100
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in Garfield County, ranked by DC Readiness.

Sites near EC Coal Garfield County
SiteTypeVoltageCapacityQueue waitScore
Greenfield (SIGURD - GLEN CANYON)Greenfield230 kV300 MW5.7 yrs55.0
Greenfield (SIGURD - GLEN CANYON)Greenfield230 kV300 MW5.7 yrs52.3
Mine SiteFormer Mine38.6
Mine SiteFormer Mine38.3
DIXIE NATIONAL FORESTFederal Excess38.2
Mine SiteFormer Mine37.8
Mine SiteFormer Mine37.5
CRSP, GLEN CANYON UNITFederal Excess37.1

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for EC Coal Garfield County, Garfield County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.