UNKNOWN201831

Substation-Adjacent

Garfield County, Utah · WECC

DC Readiness
51.7
Fair / 100

UNKNOWN201831 is a substation-adjacent datacenter candidate site in Garfield County, Utah, interconnecting through WECC. It screens at 51.7/100 DC Readiness with a catalogued 50 MW of candidate capacity and a 6.9 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN201831
Substation distance0.0 mi
Substation voltage69 kV
Available capacity50 MW
UtilityGARKANE ENERGY COOP, INCcooperativefavorable to large load · state default

Speed to power

Interconnection outlookConstrained
≈ 6.9 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionWECC
Queue depth34
Avg queue wait6.9 yrs

Connectivity

Nearest IXPTonaquint Data Center - Saint George
IXP distance119.5 mi
Fiber providers2
Fiber coverage72.2%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score85/100

Location context

Nearest datacenterLumen
DC distance116.9 mi
County hazard (FEMA NRI)Relatively Low (15)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.28¢/kWh
Industrial electricity7.05¢/kWh
Cooling degree days1,000
Heating degree days5,500
Land price / acre$4,398

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Enterprise Zone tax credits; Economic Development Tax Increment Financing (EDTIF).

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track UNKNOWN201831

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
46
Speed to power20%
57
Fiber connectivity12%
61
Energy cost10%
50
Water risk7%
24
Natural hazard6%
85
Buildability7%
60
Labor market4%
50
DC cluster4%
20
Land / acreage3%
51
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
75

Nearby comparable sites

Other scored datacenter candidate sites in Garfield County, ranked by DC Readiness.

Sites near UNKNOWN201831
SiteTypeVoltageCapacityQueue waitScore
EC Coal Garfield CountyGreenfield——1.7 yrs57.2
UNKNOWN207901Substation-Adjacent69 kV50 MW6.9 yrs50.9
TAP207900Substation-Adjacent69 kV50 MW6.9 yrs50.7
Mine SiteFormer Mine——6.9 yrs47.8
Mine SiteFormer Mine——6.9 yrs47.5
DIXIE NATIONAL FORESTFederal Excess——6.9 yrs47.5
Mine SiteFormer Mine——6.9 yrs47.0
Mine SiteFormer Mine——6.9 yrs46.8

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.