54.0
Fair / 100

EC Coal Daggett County is a greenfield datacenter candidate site in Daggett County, Utah, interconnecting through WECC. It screens at 54.0/100 DC Readiness and a 1.7 yrs average interconnection-queue wait.

Power & interconnection

Utility commercial rate0.09¢/kWh

Speed to power

ISO / RTO regionWECC
Queue depth74
Avg queue wait1.7 yrs
Recent queue wait1.0 yrs
Completion rate17%
Withdrawal rate84%

Connectivity

Nearest IXPSTRATA Vernal Data Center
IXP distance29.8 mi
Fiber providers2
Fiber coverage43.1%
Nearest cloud providerGCP
Nearest cloud regionus-west3
Cloud region distance124.9 mi

Site characteristics

Site typeGreenfield
Parcel ownerBRIDGER VALLEY ELEC ASSN, INC
Land owner typeprivate
Buildability40.0/100
Land cover (NLCD)Evergreen Forest
Former usecoal adjacent

Risk & environment

Flood zoneZone X
Water stress (WRI)3.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score85/100
Construction cost index86.7 (avg 100)

Location context

Nearest datacenterStrata Networks
DC distance29.8 mi
Nearest rail2.4 mi
Nearest gas pipeline4.9 mi
Nearest fiber route91.8 mi
County hazard (FEMA NRI)Relatively Low (15)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity9.00¢/kWh
Industrial electricity9.13¢/kWh
Cooling degree days1,000
Heating degree days5,500
Land price / acre$3,609

Incentive detail: Enterprise Zone tax credits; Economic Development Tax Increment Financing (EDTIF).

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
34
Fiber connectivity12%
61
Energy cost10%
96
Water risk8%
35
Natural hazard8%
85
Buildability7%
40
Labor market4%
50
DC cluster4%
65
Land / acreage3%
50
Construction cost3%
78
Gas pipeline2%
84
Tax incentive2%
100
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in Daggett County, ranked by DC Readiness.

Sites near EC Coal Daggett County
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN205944Substation-Adjacent138 kV100 MW1.7 yrs65.1
FLAMING GORGESubstation-Adjacent230 kV300 MW1.7 yrs64.8
TAP205943Substation-Adjacent138 kV100 MW1.7 yrs63.7
UNKNOWN202533Substation-Adjacent138 kV100 MW1.7 yrs63.4
LITTLE MOUNTAINSubstation-Adjacent230 kV300 MW1.7 yrs59.8
Greenfield (VERNAL - FLAMING GORGE)Greenfield138 kV100 MW1.7 yrs59.8
Greenfield (LITTLE MOUNTAIN - FLAMING GORG)Greenfield230 kV300 MW1.7 yrs58.9
Greenfield (FIREHOLE - LITTLE MOUNTAIN)Greenfield230 kV300 MW1.7 yrs57.5

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.