EC Near Ridgewood Providence Power

Greenfield

Providence County, Rhode Island · ISO-NE

DC Readiness
57.1
Good / 100

EC Near Ridgewood Providence Power is a greenfield datacenter candidate site in Providence County, Rhode Island, interconnecting through ISO-NE. It screens at 57.1/100 DC Readiness and a 3.5 yrs average interconnection-queue wait.

Power & interconnection

LMP zoneISONE_RI
Wholesale LMP$68.81/MWh
Utility commercial rate0.17¢/kWh

Speed to power

ISO / RTO regionISO-NE
Queue depth16
Avg queue wait3.5 yrs
Recent queue wait3.5 yrs
Completion rate25%
Withdrawal rate75%

Connectivity

Nearest IXPProv.net PVD2 (304 Carpenter)
IXP distance8.3 mi
Fiber providers4
Fiber coverage71.1%
Nearest cloud providerAWS
Nearest cloud regionus-east-1
Cloud region distance364.1 mi

Site characteristics

Site typeGreenfield
Parcel ownerFITCHBURG GAS AND ELECTRIC LIGHT COMPANY
Land owner typeprivate
Buildability50.0/100
Former usenear retired gas plant (5km)

Risk & environment

Flood zoneZone A (SFHA)
Water stress (WRI)0.50
Wetlands (NWI)Present
Critical habitatClear
Superfund nearbyClear
Hazard sub-score57/100
Construction cost index101.1 (avg 100)

Location context

Nearest datacenterProv.net PVD1 (1155 Westminster)
DC distance8.4 mi
Nearest rail6.9 mi
Nearest gas pipeline4.8 mi
Nearest fiber route40.8 mi
County hazard (FEMA NRI)Relatively Low (18)
DC tax incentiveNo
Commercial electricity17.01¢/kWh
Industrial electricity17.99¢/kWh
Cooling degree days600
Heating degree days5,600
Land price / acre$18,606

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
53
Fiber connectivity12%
87
Energy cost10%
58
Water risk8%
90
Natural hazard8%
57
Buildability7%
50
Labor market4%
50
DC cluster4%
80
Land / acreage3%
30
Construction cost3%
66
Gas pipeline2%
85
Tax incentive2%
0
Climate / cooling2%
95

Nearby comparable sites

Other scored datacenter candidate sites in Providence County, ranked by DC Readiness.

Sites near EC Near Ridgewood Providence Power
SiteTypeVoltageCapacityQueue waitScore
ANP BLACKSTONE ENERGY PROJECTSubstation-Adjacent345 kV600 MW3.5 yrs72.9
OCEAN STATESubstation-Adjacent345 kV600 MW3.5 yrs72.3
BELLINGHAM COGENERATION FACILITYSubstation-Adjacent345 kV600 MW3.5 yrs70.6
TAP156254Substation-Adjacent115 kV100 MW3.5 yrs69.9
ADMIRAL STREETSubstation-Adjacent115 kV100 MW3.5 yrs69.8
HARTFORD AVENUESubstation-Adjacent115 kV100 MW3.5 yrs69.4
POINT STREETSubstation-Adjacent115 kV100 MW3.5 yrs69.4
BERRY STREETSubstation-Adjacent345 kV600 MW3.5 yrs69.1

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.