OZ Bristol

Greenfield

Bristol County, Rhode Island · ISO-NE

DC Readiness
54.8
Fair / 100

OZ Bristol is a greenfield datacenter candidate site in Bristol County, Rhode Island, interconnecting through ISO-NE. It screens at 54.8/100 DC Readiness and a 3.5 yrs average interconnection-queue wait.

Power & interconnection

LMP zoneISONE_RI
Wholesale LMP$68.81/MWh
Utility commercial rate0.17¢/kWh

Speed to power

ISO / RTO regionISO-NE
Queue depth16
Avg queue wait3.5 yrs
Recent queue wait3.5 yrs
Completion rate25%
Withdrawal rate75%

Connectivity

Nearest IXPProv.net 935
IXP distance12.7 mi
Fiber providers4
Fiber coverage11.1%
Nearest cloud providerAWS
Nearest cloud regionus-east-1
Cloud region distance373.9 mi

Site characteristics

Site typeGreenfield
Parcel ownerFITCHBURG GAS AND ELECTRIC LIGHT COMPANY
Land owner typeprivate
Buildability50.0/100

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteCOUNTY CLEANSERS
Hazard sub-score72/100
Construction cost index87.9 (avg 100)

Location context

Nearest datacenterProv.net PVD1 (1155 Westminster)
DC distance12.8 mi
Nearest rail2.3 mi
Nearest gas pipeline4.6 mi
Nearest fiber route49.8 mi
County hazard (FEMA NRI)Relatively Low (18)
DC tax incentiveNo
Commercial electricity16.92¢/kWh
Industrial electricity18.04¢/kWh
Cooling degree days600
Heating degree days5,600
Land price / acre$49,530

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
53
Fiber connectivity12%
50
Energy cost10%
58
Water risk8%
94
Natural hazard8%
72
Buildability7%
50
Labor market4%
50
DC cluster4%
80
Land / acreage3%
38
Construction cost3%
77
Gas pipeline2%
85
Tax incentive2%
0
Climate / cooling2%
95

Nearby comparable sites

Other scored datacenter candidate sites in Bristol County, ranked by DC Readiness.

Sites near OZ Bristol
SiteTypeVoltageCapacityQueue waitScore
FALL RIVERSubstation-Adjacent345 kV600 MW3.5 yrs68.8
TAP140908Substation-Adjacent115 kV100 MW3.5 yrs68.1
TAP136310Substation-Adjacent115 kV100 MW3.5 yrs66.8
LINCOLN AVENUESubstation-Adjacent115 kV100 MW3.5 yrs66.8
WAMPANOUGSubstation-Adjacent115 kV100 MW3.5 yrs66.8
PAWTUCKETSubstation-Adjacent115 kV100 MW3.5 yrs65.8
Forbes Street Solar Project II (FSSPII)Brownfield4 MW65.8
MINK STREETSubstation-Adjacent115 kV100 MW3.5 yrs65.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for OZ Bristol, Bristol County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.