Columbia Plateau Conservation at 45.596, -119.570

Federal Excess

Morrow, Oregon · WECC

DC Readiness
49.5
Fair / 100

At a glance

Columbia Plateau Conservation at 45.596, -119.570 is a federal excess datacenter candidate site in Morrow, Oregon, scoring 49.5/100 DC Readiness — 38th of 43 scored sites in the county. It sits in the WECC grid region and the COLUMBIA BASIN ELEC COOPERATIVE, INC service territory, where interconnection has averaged 3.5 years from request to operation.

Power & interconnection

UtilityCOLUMBIA BASIN ELEC COOPERATIVE, INCnot available

Speed to power

Interconnection outlookConstrained
≈ 5.5 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionWECC
Queue depth34
Avg queue wait3.5 yrs
Recent queue wait5.5 yrs
Completion rate17%
Withdrawal rate84%

Connectivity

Nearest IXPKNWCWAXA - Kennewick Central Office
IXP distance46.4 mi
Fiber providers6
Fiber coverage26.2%

Site characteristics

Acreage46 ac
Buildable load (est.)~18–46 MWland-based
Former useResearch and Development

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Medium-High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score78/100

Location context

Nearest datacenterPercheron DC
DC distance14.4 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity6.53¢/kWh
Industrial electricity6.50¢/kWh
Cooling degree days300
Heating degree days4,700
Land price / acre$2,202

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Enterprise Zone property tax exemption for 3-15 years; no sales tax in Oregon.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track COLUMBIA PLATEAU CONSERVATION

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

How does Columbia Plateau Conservation at 45.596, -119.570 compare with other sites in Morrow?

Columbia Plateau Conservation at 45.596, -119.570 ranks 38th of 43 scored candidate sites in Morrow. Its 49.5/100 is about 10% below the county average of 55.2. It is roughly in line with the Oregon average of 53.1 and roughly in line with the national average of 53.2.

Against the Oregon average, its strongest sub-score is natural hazard (78 vs 77) and its weakest is fiber connectivity (48 vs 66). Power and speed to power each carry 20% of the composite score, fiber 12%, water 7% and hazard 6%.

How close is Columbia Plateau Conservation at 45.596, -119.570 to power, fiber and other datacenters?

For connectivity, the nearest internet exchange facility is KNWCWAXA - Kennewick Central Office at 46.4 miles. 6 fiber providers report service at the location in FCC broadband data. The closest operating datacenter on record is Percheron DC, 14.4 miles away.

What are the flood, water and hazard risks at Columbia Plateau Conservation at 45.596, -119.570?

At the county level, FEMA's National Risk Index rates Morrow "Relatively Low".

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
50
Fiber connectivity12%
48
Energy cost10%
50
Water risk7%
60
Natural hazard6%
78
Buildability7%
50
Labor market4%
50
DC cluster4%
80
Land / acreage3%
49
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
100

Nearby comparable sites

Other scored datacenter candidate sites in Morrow, ranked by DC Readiness.

Sites near Columbia Plateau Conservation at 45.596, -119.570
SiteTypeVoltageCapacityQueue waitScore
CALPINESubstation-Adjacent500 kV1,000 MW3.5 yrs66.3
BoardmanBrownfield—642 MW3.5 yrs64.8
UNKNOWN201297Substation-Adjacent230 kV300 MW3.5 yrs61.9
EC Near BoardmanGreenfield——3.5 yrs59.3
EC Near BoardmanGreenfield——3.5 yrs59.3
EC Near BoardmanGreenfield——3.5 yrs59.3
EC Near BoardmanGreenfield——3.5 yrs58.9
EC Near BoardmanGreenfield——3.5 yrs58.7

Columbia Plateau Conservation at 45.596, -119.570: common questions

What is the DC Readiness score of Columbia Plateau Conservation at 45.596, -119.570?

Columbia Plateau Conservation at 45.596, -119.570 scores 49.5/100 on the GridCensus DC Readiness scale, rated fair. It ranks 38th of 43 scored sites in Morrow. The Morrow average is 55.2 and the Oregon average is 53.1.

Which electric utility serves Columbia Plateau Conservation at 45.596, -119.570?

COLUMBIA BASIN ELEC COOPERATIVE, INC (not available) holds the retail service territory that contains the site.

What grid region is Columbia Plateau Conservation at 45.596, -119.570 in?

Columbia Plateau Conservation at 45.596, -119.570 is in the WECC region. Projects interconnecting there have averaged a 3.5-year wait from queue request to operation.

How far is Columbia Plateau Conservation at 45.596, -119.570 from an internet exchange?

The nearest internet exchange facility is KNWCWAXA - Kennewick Central Office, about 46.4 miles away; 6 fiber providers report service at the location.

Related pages

About this data

Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published October 10, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “Columbia Plateau Conservation at 45.596, -119.570, Morrow, OR”, https://gridcensus.com/datacenter-sites/oregon/morrow/columbia-plateau-conservation-4fcf2e9a (data as of October 10, 2026).

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for Columbia Plateau Conservation at 45.596, -119.570, Morrow is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.