EC Coal Rogers County

Greenfield

Rogers, Oklahoma · SPP

DC Readiness
59.8
Good / 100

EC Coal Rogers County is a greenfield datacenter candidate site in Rogers, Oklahoma, interconnecting through SPP. It screens at 59.8/100 DC Readiness and a 3.5 yrs average interconnection-queue wait.

Power & interconnection

LMP zoneSPP_SOUTH
Wholesale LMP$15.62/MWh
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionSPP
Queue depth87
Avg queue wait3.5 yrs
Recent queue wait3.5 yrs
Completion rate16%
Withdrawal rate84%

Connectivity

Nearest IXPTulsaConnect DC3
IXP distance17.8 mi
Fiber providers7
Fiber coverage46.4%
Nearest cloud providerGCP
Nearest cloud regionus-south1
Cloud region distance253.6 mi

Site characteristics

Site typeGreenfield
Parcel ownerPUBLIC SERVICE CO OF OKLAHOMA
Land owner typeprivate
Buildability80.0/100
Land cover (NLCD)Grassland/Herbaceous
Former usecoal adjacent

Risk & environment

Flood zoneZone X
Water stress (WRI)1.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score58/100
Construction cost index75.9 (avg 100)

Location context

Nearest datacenterCherokee Data Center
DC distance10.3 mi
Nearest rail4.4 mi
Nearest gas pipeline0.6 mi
Nearest fiber route45.7 mi
County hazard (FEMA NRI)Relatively High (42)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.94¢/kWh
Industrial electricity8.32¢/kWh
Cooling degree days1,900
Heating degree days3,600
Land price / acre$3,964

Incentive detail: Sales tax exemption on DC equipment; 5-year ad valorem tax exemption.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
40
Fiber connectivity12%
72
Energy cost10%
93
Water risk8%
72
Natural hazard8%
58
Buildability7%
80
Labor market4%
50
DC cluster4%
80
Land / acreage3%
49
Construction cost3%
87
Gas pipeline2%
98
Tax incentive2%
100
Climate / cooling2%
30

Nearby comparable sites

Other scored datacenter candidate sites in Rogers, ranked by DC Readiness.

Sites near EC Coal Rogers County
SiteTypeVoltageCapacityQueue waitScore
NORTHEASTERN (345KV)Substation-Adjacent345 kV600 MW3.4 yrs71.3
UNKNOWN119438Substation-Adjacent161 kV100 MW3.4 yrs69.9
UNKNOWN119012Substation-Adjacent161 kV100 MW3.4 yrs68.7
Greenfield (ONETA - NORTHEASTERN (345KV))Greenfield345 kV600 MW3.4 yrs68.6
TAP149304Substation-Adjacent138 kV100 MW3.4 yrs68.4
UNKNOWN119692Substation-Adjacent138 kV100 MW3.4 yrs68.4
Greenfield (TULSA NORTH (345KV) - NORTHEAS)Greenfield345 kV600 MW3.4 yrs67.9
UNKNOWN119381Substation-Adjacent138 kV100 MW3.4 yrs67.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for EC Coal Rogers County, Rogers. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.