Skip to content
Gridcensus

Greenfield (CARROLL - UNKNOWN157576)

Greenfield

Red River Parish, Ohio · PJM

DC Readiness
51.0
Fair / 100

Greenfield (CARROLL - UNKNOWN157576) is a greenfield datacenter candidate site in Red River Parish, Ohio, interconnecting through PJM. It screens at 51.0/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 3.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationCARROLL
Substation voltage230 kV
Available capacity300 MW

Speed to power

Interconnection outlookModerate
≈ 3.8 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionPJM
Queue depth11
Avg queue wait3.8 yrs

Connectivity

Nearest IXPDartPoints Shreveport, LA - SHV1
IXP distance44.4 mi
Fiber providers2
Fiber coverage30.5%

Site characteristics

Site typeGreenfield

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score42/100

Location context

Nearest datacenterDartPoints Shreveport, LA - SHV1
DC distance44.4 mi
County hazard (FEMA NRI)Very High (58)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.12¢/kWh
Industrial electricity7.54¢/kWh
Cooling degree days2,700
Heating degree days1,700
Land price / acre$2,663

Regulatory climate

Moderatestate posture · as of 2026-08

DC tax incentives paused for 2026; AEP Ohio large-load tariff in force.

DC tax incentiveNo / suspended
Large-load threshold≥ 25 MW

AEP Ohio tariff: ≥25 MW, 85% take-or-pay, on-site-gen curtailment sync.

Incentive detail: Industrial Tax Exemption Program (ITEP) up to 80% property tax abatement for 10 years.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Greenfield (CARROLL - UNKNOWN157576)

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
50
Speed to power20%
46
Fiber connectivity12%
54
Energy cost10%
50
Water risk7%
88
Natural hazard6%
42
Buildability7%
50
Labor market4%
50
DC cluster4%
40
Land / acreage3%
48
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
0

Nearby comparable sites

Other scored datacenter candidate sites in Red River Parish, ranked by DC Readiness.

Sites near Greenfield (CARROLL - UNKNOWN157576)
SiteTypeVoltageCapacityQueue waitScore
Mansfield MillBrownfield—25 MW1.4 yrs62.3
UNKNOWN157576Substation-Adjacent500 kV1,000 MW2.8 yrs59.6
EC Near Mansfield MillGreenfield——1.4 yrs56.7
EC Near Mansfield MillGreenfield——1.4 yrs55.8
CARROLLSubstation-Adjacent230 kV300 MW2.8 yrs55.4
UNKNOWN112571Substation-Adjacent230 kV300 MW2.8 yrs54.9
EC Near Mansfield MillGreenfield——1.4 yrs54.8
EC Near Mansfield MillGreenfield——1.4 yrs54.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for Greenfield (CARROLL - UNKNOWN157576), Red River Parish is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.