DC Readiness
52.8
Fair / 100

SILAS LITTLE EF BLDGS is a federal excess datacenter candidate site in Burlington County, New Jersey, interconnecting through SPP. It screens at 52.8/100 DC Readiness and a 3.3 yrs average interconnection-queue wait.

Power & interconnection

Speed to power

Interconnection outlookModerate
≈ 3.3 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionSPP
Queue depth1
Avg queue wait3.3 yrs

Connectivity

Nearest IXPQTS Princeton (PJC1)
IXP distance25.2 mi
Fiber providers9
Fiber coverage38.6%

Site characteristics

Acreage5 ac
Buildable load (est.)~2–5 MWland-based
Former useResearch and Development

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score72/100

Location context

Nearest datacenterQTS Princeton (PJC1)
DC distance25.2 mi
County hazard (FEMA NRI)Relatively Moderate (28)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.16¢/kWh
Industrial electricity7.51¢/kWh
Cooling degree days1,000
Heating degree days4,900
Land price / acre$12,875

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: UEZ sales tax exemption (reduced rate); BEIP/Grow NJ incentives for job creation.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track SILAS LITTLE EF BLDGS

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
58
Fiber connectivity12%
58
Energy cost10%
50
Water risk7%
84
Natural hazard6%
72
Buildability7%
50
Labor market4%
50
DC cluster4%
60
Land / acreage3%
17
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
75

Nearby comparable sites

Other scored datacenter candidate sites in Burlington County, ranked by DC Readiness.

Sites near SILAS LITTLE EF BLDGS
SiteTypeVoltageCapacityQueue waitScore
EC Coal Burlington CountyGreenfield——2.6 yrs61.7
EC Coal Burlington CountyGreenfield——2.6 yrs61.6
UNKNOWN132248Substation-Adjacent230 kV300 MW3.8 yrs61.4
OZ BurlingtonGreenfield——2.6 yrs61.3
OZ BurlingtonGreenfield——2.6 yrs61.2
LUMBERTONSubstation-Adjacent230 kV300 MW3.8 yrs61.0
EC Near PSEG Burlington Generating StationGreenfield——2.6 yrs60.5
EC Near PSEG Burlington Generating StationGreenfield——2.6 yrs59.5

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for SILAS LITTLE EF BLDGS, Burlington County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.