DC Readiness
50.3
Fair / 100

Frenchman-Cambridge (P-S) is a federal excess datacenter candidate site in Furnas, Nebraska, interconnecting through SPP. It screens at 50.3/100 DC Readiness and a 4.3 yrs average interconnection-queue wait.

Power & interconnection

UtilityTWIN VALLEYS PUBLIC POWER DISTnot availablefavorable to large load · state default

Speed to power

Interconnection outlookModerate
≈ 4.9 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionSPP
Queue depth25
Avg queue wait4.3 yrs
Recent queue wait4.9 yrs
Completion rate16%
Withdrawal rate84%

Connectivity

Nearest IXPBeloit-NOC
IXP distance102.2 mi
Fiber providers4
Fiber coverage75.2%

Site characteristics

Acreage8 ac
Buildable load (est.)~3–8 MWland-based
Former useReclamation and Irrigation

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Medium-High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score72/100

Location context

Nearest datacenterCompute North
DC distance48.6 mi
County hazard (FEMA NRI)Relatively Moderate (28)
DC tax incentiveYes (sales_tax_exemption)
Cooling degree days1,000
Heating degree days6,200
Land price / acre$2,895

Regulatory climate

Favorablestate posture · as of 2026-08

Public-power incentives; DC-friendly.

DC tax incentiveYes

Incentive detail: ImagiNE Nebraska Act: sales tax exemption on DC equipment; investment tax credits.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Frenchman-Cambridge (P-S)

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
54
Fiber connectivity12%
69
Energy cost10%
50
Water risk7%
60
Natural hazard6%
72
Buildability7%
50
Labor market4%
50
DC cluster4%
40
Land / acreage3%
37
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
75

Nearby comparable sites

Other scored datacenter candidate sites in Furnas, ranked by DC Readiness.

Sites near Frenchman-Cambridge (P-S)
SiteTypeVoltageCapacityQueue waitScore
EC Near CambridgeGreenfield——4.3 yrs58.9
EC Near CambridgeGreenfield——4.3 yrs58.8
EC Near CambridgeGreenfield——4.3 yrs58.5
EC Near CambridgeGreenfield——4.3 yrs58.3
EC Near CambridgeGreenfield——4.3 yrs57.9
EC Near CambridgeGreenfield——4.3 yrs57.9
EC Near CambridgeGreenfield——4.3 yrs57.9
EC Near CambridgeGreenfield——4.3 yrs57.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for Frenchman-Cambridge (P-S), Furnas is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.