DC Readiness
58.5
Good / 100

Johnson is a brownfield datacenter candidate site in Stanton, Kansas, interconnecting through SPP. It screens at 58.5/100 DC Readiness with a catalogued 4 MW of candidate capacity and a 3.5 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN119525
Nearest grid bottleneckCIMXF2CIMXF3 · 129 km (SPP)
Substation distance1.3 mi
Substation voltage115 kV
Available capacity4 MW
LMP zoneSPP_NORTH
Wholesale LMP$21.13/MWh
Utility commercial rate0.09¢/kWh
UtilityPIONEER ELECTRIC COOP, INC - (KS)cooperativefavorable to large load · state default

Speed to power

Interconnection outlookModerate
≈ 3.5 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionSPP
Queue depth64
Avg queue wait3.5 yrs
Recent queue wait3.5 yrs
Completion rate16%
Withdrawal rate84%

Connectivity

Fiber providers1
Fiber coverage79.1%
Nearest cloud providerGCP
Nearest cloud regionus-central1
Cloud region distance404.8 mi

Site characteristics

Site typeBrownfield
Parcel ownerCity of Johnson
Land contactState Environmental Cleanup Program
Land owner typeprivate
Buildability95.0/100
Land cover (NLCD)Developed, Medium Intensity
Former useoil
Existing capacity4 MW
Retirement date2017-08-01

Risk & environment

Environmental constraintLow (30/100)
Flood zoneZone X
Water stress (WRI)2.40
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteD D AUTO REPAIR
Hazard sub-score55/100
Construction cost index89.0 (avg 100)

Location context

Nearest rail0.3 mi
Nearest gas pipeline14.5 mi
Nearest fiber route195.0 mi
County hazard (FEMA NRI)Relatively High (35)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity8.95¢/kWh
Industrial electricity5.94¢/kWh
Cooling degree days1,400
Heating degree days5,000
Land price / acre$1,446

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: PEAK program payroll tax incentives; IRB property tax exemptions available.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Johnson

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
36
Speed to power20%
53
Fiber connectivity12%
72
Energy cost10%
90
Water risk7%
52
Natural hazard6%
55
Buildability7%
95
Labor market4%
50
DC cluster4%
10
Land / acreage3%
76
Construction cost3%
76
Gas pipeline2%
53
Tax incentive1%
100
Climate / cooling1%
55

Nearby comparable sites

Other scored datacenter candidate sites in Stanton, ranked by DC Readiness.

Sites near Johnson
SiteTypeVoltageCapacityQueue waitScore
EC Near JohnsonGreenfield——3.5 yrs59.3
EC Near JohnsonGreenfield——3.5 yrs59.0
EC Near JohnsonGreenfield——3.5 yrs57.1
EC Near JohnsonGreenfield——3.5 yrs57.0
EC Near JohnsonGreenfield——3.5 yrs56.0
EC Near JohnsonGreenfield——3.5 yrs55.9
UNKNOWN119526Substation-Adjacent115 kV100 MW3.3 yrs55.1
UNKNOWN119533Substation-Adjacent115 kV100 MW3.3 yrs54.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Johnson, Stanton. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.