OZ Decatur

Greenfield

Decatur, Iowa · MISO

DC Readiness
59.0
Good / 100

At a glance

OZ Decatur is a greenfield datacenter candidate site in Decatur, Iowa, scoring 59.0/100 DC Readiness — 1st of 2 scored sites in the county. It sits in the MISO grid region and the INTERSTATE POWER AND LIGHT CO service territory, where interconnection has averaged 4.3 years from request to operation.

Power & interconnection

LMP zoneMISO_MINN
Wholesale LMP$34.82/MWh
Utility commercial rate0.13¢/kWh
UtilityINTERSTATE POWER AND LIGHT COinvestor ownedfavorable to large load · terms ≥ 100 MW

Speed to power

Interconnection outlookModerate
≈ 4.9 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionMISO
Queue depth112
Avg queue wait4.3 yrs
Recent queue wait4.9 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPAureon West Des Moines
IXP distance59.0 mi
Fiber providers2
Fiber coverage98.7%
Nearest cloud providerAzure
Nearest cloud regioncentralus
Cloud region distance88.6 mi

Site characteristics

Site typeGreenfield
Land contactDecatur County Assessor
Land owner typeprivate
Buildability75.0/100
Land cover (NLCD)Pasture/Hay

Risk & environment

Environmental constraintNone (0/100)
Flood zoneZone X
Water stress (WRI)0.60
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score70/100
Construction cost index55.9 (avg 100)

Location context

Nearest datacenterMicrosoft
DC distance51.6 mi
Nearest rail19.5 mi
Nearest gas pipeline3.9 mi
Nearest fiber route33.7 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity13.42¢/kWh
Industrial electricity8.19¢/kWh
Cooling degree days900
Heating degree days6,500
Land price / acre$5,732

Regulatory climate

Favorablestate posture · as of 2026-08

Strong incentives; utilities courting hyperscale load.

DC tax incentiveYes

Incentive detail: Sales tax exemption on DC equipment for $1M+ investments; property tax phase-in for new construction.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 1 nearby

Get alerts

Track OZ Decatur

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

How does OZ Decatur compare with other sites in Decatur?

OZ Decatur ranks 1st of 2 scored candidate sites in Decatur. Its 59.0/100 is roughly in line with the county average of 58.2. It is roughly in line with the Iowa average of 56.4 and about 11% above the national average of 53.2.

Against the Iowa average, its strongest sub-score is natural hazard (70 vs 69) and its weakest is fiber connectivity (61 vs 77). Power and speed to power each carry 20% of the composite score, fiber 12%, water 7% and hazard 6%.

How close is OZ Decatur to power, fiber and other datacenters?

The nearest located transmission bottleneck is ALW16X26_WAPELLO_TR91_TR91 (MISO), 83 miles away. For connectivity, the nearest internet exchange facility is Aureon West Des Moines at 59 miles. 2 fiber providers report service at the location in FCC broadband data. The closest operating datacenter on record is Microsoft, 51.6 miles away.

What are the flood, water and hazard risks at OZ Decatur?

The site is in FEMA flood zone X, outside the Special Flood Hazard Area (minimal or moderate flood risk). WRI rates baseline water stress at 0.60 on a 0–5 scale. No mapped wetlands are recorded on the parcel. At the county level, FEMA's National Risk Index rates Decatur "Relatively Moderate".

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
50
Fiber connectivity12%
61
Energy cost10%
84
Water risk7%
88
Natural hazard6%
70
Buildability7%
75
Labor market4%
50
DC cluster4%
50
Land / acreage3%
39
Construction cost3%
100
Gas pipeline2%
87
Tax incentive1%
100
Climate / cooling1%
80

Nearby comparable sites

Other scored datacenter candidate sites in Decatur, ranked by DC Readiness.

Sites near OZ Decatur
SiteTypeVoltageCapacityQueue waitScore
OZ DecaturGreenfield——4.3 yrs57.3

OZ Decatur: common questions

What is the DC Readiness score of OZ Decatur?

OZ Decatur scores 59.0/100 on the GridCensus DC Readiness scale, rated good. It ranks 1st of 2 scored sites in Decatur. The Decatur average is 58.2 and the Iowa average is 56.4.

Which electric utility serves OZ Decatur?

INTERSTATE POWER AND LIGHT CO (investor owned) holds the retail service territory that contains the site; its holding company is ALLIANT ENERGY CORP.

What grid region is OZ Decatur in?

OZ Decatur is in the MISO region. Projects interconnecting there have averaged a 4.3-year wait from queue request to operation.

Is OZ Decatur in a flood zone?

The site is in FEMA flood zone X, outside the Special Flood Hazard Area (minimal or moderate flood risk).

Who owns OZ Decatur?

Parcel records list the owner as MIDAMERICAN ENERGY CO (private land).

How far is OZ Decatur from an internet exchange?

The nearest internet exchange facility is Aureon West Des Moines, about 59 miles away; 2 fiber providers report service at the location.

Related pages

About this data

Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published October 10, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “OZ Decatur, Decatur, IA”, https://gridcensus.com/datacenter-sites/iowa/decatur/oz-decatur-48a5af17 (data as of October 10, 2026).

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for OZ Decatur, Decatur is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.