EC Near Greenleaf 1

Greenfield

Sutter County, California · CAISO

DC Readiness
47.3
Fair / 100

EC Near Greenleaf 1 is a greenfield datacenter candidate site in Sutter County, California, interconnecting through CAISO. It screens at 47.3/100 DC Readiness and a 5.7 yrs average interconnection-queue wait.

Power & interconnection

LMP zoneCAISO_NP15
Wholesale LMP$16.53/MWh
Utility commercial rate0.28¢/kWh

Speed to power

ISO / RTO regionCAISO
Queue depth480
Avg queue wait5.7 yrs
Recent queue wait3.0 yrs
Completion rate11%
Withdrawal rate89%

Connectivity

Nearest IXPQuest Roseville
IXP distance33.6 mi
Fiber providers5
Fiber coverage65.8%
Nearest cloud providerAzure
Nearest cloud regionwestus
Cloud region distance98.4 mi

Site characteristics

Site typeGreenfield
Land contactSutter County Assessor
Land owner typeprivate
Buildability65.0/100
Land cover (NLCD)Cultivated Crops
Former usenear retired gas plant (10km)

Risk & environment

Flood zoneZone X
Water stress (WRI)3.80
Wetlands (NWI)Present
Critical habitatClear
Superfund nearbyClear
Hazard sub-score42/100
Construction cost index111.5 (avg 100)

Location context

Nearest datacenterQuest Roseville
DC distance33.6 mi
Nearest rail9.1 mi
Nearest gas pipeline0.1 mi
Nearest fiber route1.9 mi
County hazard (FEMA NRI)Relatively High (48)
DC tax incentiveNo
Commercial electricity28.03¢/kWh
Industrial electricity21.55¢/kWh
Cooling degree days1,000
Heating degree days2,500
Land price / acre$14,191

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
35
Fiber connectivity12%
66
Energy cost10%
63
Water risk8%
49
Natural hazard8%
42
Buildability7%
65
Labor market4%
50
DC cluster4%
45
Land / acreage3%
34
Construction cost3%
57
Gas pipeline2%
100
Tax incentive2%
0
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in Sutter County, ranked by DC Readiness.

Sites near EC Near Greenleaf 1
SiteTypeVoltageCapacityQueue waitScore
Sierra Pacific Lincoln FacilityBrownfield66 kV13 MW5.7 yrs56.3
O'BANIONSubstation-Adjacent500 kV1,000 MW8.2 yrs53.6
RIO OSOSubstation-Adjacent230 kV300 MW8.2 yrs53.0
Western Regional Sanitary LandfillBrownfield115 kV0 MW8.2 yrs52.7
TAP302769Substation-Adjacent115 kV100 MW8.2 yrs51.6
EC Near Greenleaf 1Greenfield5.7 yrs50.9
SUTTERSubstation-Adjacent230 kV300 MW8.2 yrs50.8
LINCOLNSubstation-Adjacent115 kV100 MW8.2 yrs49.8

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.