OZ San Joaquin

Greenfield

San Joaquin County, California · CAISO

DC Readiness
53.3
Fair / 100

OZ San Joaquin is a greenfield datacenter candidate site in San Joaquin County, California, interconnecting through CAISO. It screens at 53.3/100 DC Readiness and a 5.7 yrs average interconnection-queue wait.

Power & interconnection

LMP zoneCAISO_NP15
Wholesale LMP$16.53/MWh
Utility commercial rate0.28¢/kWh

Speed to power

ISO / RTO regionCAISO
Queue depth311
Avg queue wait5.7 yrs
Recent queue wait3.0 yrs
Completion rate11%
Withdrawal rate89%

Connectivity

Nearest IXPEZ Network Systems
IXP distance4.3 mi
Fiber providers6
Fiber coverage34.2%
Nearest cloud providerAWS
Nearest cloud regionus-west-1
Cloud region distance53.1 mi

Site characteristics

Site typeGreenfield
Parcel ownerPACIFIC GAS & ELECTRIC COMPANY
Land owner typeprivate
Buildability95.0/100
Land cover (NLCD)Developed, Medium Intensity

Risk & environment

Flood zoneZone X
Water stress (WRI)3.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteMOE AUTO REPAIR
Hazard sub-score42/100
Construction cost index103.9 (avg 100)

Location context

Nearest datacenterEZ Network Systems
DC distance4.3 mi
Nearest rail0.2 mi
Nearest gas pipeline1.3 mi
Nearest fiber route129.8 mi
County hazard (FEMA NRI)Relatively High (48)
DC tax incentiveNo
Commercial electricity27.91¢/kWh
Industrial electricity21.32¢/kWh
Cooling degree days1,000
Heating degree days2,500
Land price / acre$20,649

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
35
Fiber connectivity12%
82
Energy cost10%
63
Water risk8%
52
Natural hazard8%
42
Buildability7%
95
Labor market4%
50
DC cluster4%
90
Land / acreage3%
30
Construction cost3%
63
Gas pipeline2%
96
Tax incentive2%
0
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in San Joaquin County, ranked by DC Readiness.

Sites near OZ San Joaquin
SiteTypeVoltageCapacityQueue waitScore
WEBERSubstation-Adjacent230 kV300 MW5.7 yrs63.2
UNKNOWN308925Substation-Adjacent115 kV100 MW5.7 yrs59.5
EIGHT MILESubstation-Adjacent230 kV300 MW5.7 yrs58.9
TRACYSubstation-Adjacent500 kV1,000 MW5.7 yrs58.7
LODI STIGSubstation-Adjacent230 kV300 MW5.7 yrs58.6
STAGGSubstation-Adjacent230 kV300 MW5.7 yrs58.5
FRENCH CAMPSubstation-Adjacent115 kV100 MW5.7 yrs57.9
UNKNOWN301727Substation-Adjacent115 kV100 MW5.7 yrs57.5

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for OZ San Joaquin, San Joaquin County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.