West Ford Flat Power Plant

Brownfield

Middletown, Lake, California · Geysers Power Co LLC

Legacy capacity
38
MW

West Ford Flat Power Plant is a former geothermal site in Middletown, Lake, California, retired 2016-12-01. Retired generation sites are among the most attractive datacenter redevelopment targets: the existing interconnection was sized for roughly 38 MW of generation, so the grid hookup, transmission rights, and often cooling-water access are already in place — collapsing the speed-to-power timeline versus a greenfield build.

Former use & capacity

Former useformer geothermal site
Site typeretired_plant
Existing capacity38 MW
Retirement date2016-12-01
EIA plant ID#10199

Grid hookup & remediation

Nearest substation0.0 mi
OperatorGeysers Power Co LLC
Operator address10350 Socrates Mine Road, Middletown, CA, 95461
Why this site is datacenter-attractive: a former geothermal site of this scale leaves behind a high-capacity grid interconnection that a new load can re-use, frequently shaving years off the interconnection queue. Retired-plant sites also tend to be already zoned for heavy industrial use with established road, rail, and water infrastructure.

Nearby datacenter candidate sites

Scored candidate sites near West Ford Flat Power Plant, ranked by DC Readiness.

Candidate sites near West Ford Flat Power Plant
SiteTypeStateCountyVoltageCapacityQueue waitScore
QUICKSILVERSubstation-AdjacentCASonoma County230 kV300 MW5.7 yrs59.2
SOCRATES 19Substation-AdjacentCASonoma County230 kV300 MW5.7 yrs58.8
COBB CREEKSubstation-AdjacentCASonoma County230 kV300 MW5.7 yrs58.7
NCPA 1&2Substation-AdjacentCASonoma County230 kV300 MW5.7 yrs58.4
LAKEVIEWSubstation-AdjacentCALake County230 kV300 MW5.7 yrs56.9
WEST FORD FLATSubstation-AdjacentCASonoma County230 kV300 MW5.7 yrs56.9
SULPHUR SPRINGSSubstation-AdjacentCASonoma County230 kV300 MW5.7 yrs56.5
CALISTOGA POWER PLANTSubstation-AdjacentCASonoma County230 kV300 MW5.7 yrs56.4

Nearby internet exchanges

See all datacenter sites in California

Dataset updated . Screening estimates derived from public data sources.

Brownfield attributes are derived from EIA retired-generator and EPA public data. Existing capacity reflects the retired plant's historical nameplate, not deliverable interconnection for a new load. Confirm reusable interconnection rights, remediation status, and site availability with the utility, ISO, and current owner.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for West Ford Flat Power Plant, Middletown, Lake, California. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.