TAP146157
SubstationNorth Carolina · VIRGINIA ELECTRIC & POWER CO
At a glance
TAP146157 is an electric transmission substation in North Carolina, on VIRGINIA ELECTRIC & POWER CO's transmission network. It is classified as high-voltage (230 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.
Voltage & classification
Ownership
Connected transmission lines
Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.
| Line ID | Voltage | Owner | Status | Length |
|---|---|---|---|---|
| #101766 | 230 kV | VIRGINIA ELECTRIC & POWER CO | IN SERVICE | 6.7 mi |
| #117428 | 230 kV | VIRGINIA ELECTRIC & POWER CO | IN SERVICE | 15.3 mi |
| #144515 | 230 kV | VIRGINIA ELECTRIC & POWER CO | IN SERVICE | 0.2 mi |
Nearby datacenter candidate sites
Scored candidate sites within roughly 25 miles of TAP146157, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.
| Site | Type | State | County | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|---|---|
| UNKNOWN111630 | Substation-Adjacent | NC | Dare County | 230 kV | 300 MW | 5.3 yrs | 53.2 |
| UNKNOWN111634 | Substation-Adjacent | NC | Dare County | 230 kV | 300 MW | 5.3 yrs | 53.2 |
| UNKNOWN111631 | Substation-Adjacent | NC | Dare County | 230 kV | 300 MW | 5.3 yrs | 53.2 |
| TAP146156 | Substation-Adjacent | NC | Dare County | 230 kV | 300 MW | 5.3 yrs | 53.2 |
| Mine Site | Former Mine | OK | Haskell | — | — | 4.3 yrs | 43.7 |
Who owns the transmission lines at TAP146157?
The 3 connected lines listed above are owned by VIRGINIA ELECTRIC & POWER CO. Line voltages range from 230 kV to 230 kV. Their combined recorded length is about 22.3 miles.
How do candidate sites near TAP146157 score?
The 5 highest-scoring candidate sites within about 25 miles range from 44 to 53 on the 0–100 DC Readiness scale. They fall in Dare County, Haskell. The North Carolina average across 2,778 scored sites is 55.1. 1,087 of those North Carolina sites are classed as substation sites (candidate locations generated at an existing substation).
Frequently asked questions
What voltage is TAP146157 substation?
TAP146157 has a maximum voltage of 230 kV. That places it in the 230–344 kV band. The median named US substation in this dataset is 115 kV, so TAP146157 is above the national midpoint.
How many transmission lines connect to TAP146157 substation?
3 transmission lines terminate at or pass through TAP146157 in the HIFLD line data. The connected lines listed here run at 230 kV. Together the listed lines cover about 22.3 miles.
Who owns TAP146157 substation?
HIFLD does not publish substation owners directly. Most of the transmission lines that end at TAP146157 belong to VIRGINIA ELECTRIC & POWER CO. GridCensus derives this from the line data, so confirm ownership with the utility for anything contractual.
Where is TAP146157 substation located?
TAP146157 is in North Carolina at 35.3522, -75.5036. The datacenter candidate sites closest to it are in Dare County, Haskell.
Are there datacenter candidate sites near TAP146157 substation?
GridCensus lists 5 scored candidate sites within roughly 25 miles of TAP146157. The highest-scoring is UNKNOWN111630 at 53/100. Across North Carolina, the average DC Readiness score is 55.1.
More in North Carolina
About this data
Source: HIFLD Electric Substations and Transmission Lines (U.S. Department of Homeland Security), as published June 29, 2026. See the methodology for how records are matched, cleaned and scored.
Cite as: GridCensus, “TAP146157 substation, North Carolina”, https://gridcensus.com/substations/north-carolina/tap146157-c16c7296 (data as of June 29, 2026).
Dataset updated . Screening estimates derived from public data sources.
Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.
Go deeper than the public screen
Every site and score for TAP146157 substation, North Carolina is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.