Skip to content
Gridcensus

EARLEYS

Substation

North Carolina · VIRGINIA ELECTRIC & POWER CO

Max voltage
230
kV

At a glance

EARLEYS is a 230 kV electric substation in North Carolina on VIRGINIA ELECTRIC & POWER CO's transmission network, recorded in the HIFLD transmission dataset. 7 transmission lines connect to it. 10 of North Carolina's 106 named substations operate in a higher voltage band. The highest-scoring datacenter candidate site within about 25 miles is BOYKINS in Southampton County, with a DC Readiness score of 60/100.

EARLEYS is an electric transmission substation in North Carolina, on VIRGINIA ELECTRIC & POWER CO's transmission network. It is classified as high-voltage (230 kv) and connects 7 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage230 kV
Voltage classHigh-voltage (230 kV)
Connected lines7

Ownership

Line owner (most lines)VIRGINIA ELECTRIC & POWER CO
Coordinates36.2564, -77.0794

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#161048230 kVVIRGINIA ELECTRIC & POWER COIN SERVICE13.8 mi
#115750230 kVVIRGINIA ELECTRIC & POWER COIN SERVICE13.7 mi
#104791230 kVVIRGINIA ELECTRIC & POWER COIN SERVICE32.7 mi
#146391230 kVVIRGINIA ELECTRIC & POWER COIN SERVICE1.8 mi
#180301115 kVVIRGINIA ELECTRIC & POWER COIN SERVICE30.1 mi
#149080—VIRGINIA ELECTRIC & POWER COIN SERVICE6.8 mi
#179604——IN SERVICE0.7 mi
#116899—VIRGINIA ELECTRIC & POWER COIN SERVICE12.5 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of EARLEYS, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near EARLEYS substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
BOYKINSSubstation-AdjacentVASouthampton County230 kV300 MW5.1 yrs60.0
TAP148239Substation-AdjacentVASouthampton County230 kV300 MW5.1 yrs59.8
UNKNOWN111380Substation-AdjacentNCGates County230 kV300 MW5.3 yrs58.6
UNKNOWN114522Substation-AdjacentVAFranklin city230 kV300 MW5.1 yrs58.4
TAP148198Substation-AdjacentNCHertford County230 kV300 MW5.3 yrs58.1
TAP148219Substation-AdjacentNCNorthampton County230 kV300 MW5.3 yrs57.5
EARLEYSSubstation-AdjacentNCHertford County230 kV300 MW5.3 yrs57.2
UNKNOWN111386Substation-AdjacentNCHertford County230 kV300 MW5.3 yrs57.1

How does EARLEYS compare with other substations in North Carolina?

North Carolina has 3,209 substation records in HIFLD, of which 106 carry a station name; the rest are unnamed tap points, risers and line ends. 54 named substations in the state are in EARLEYS's 230–344 kV band (51% of named stations). 10 sit in a higher band. 10 named substations in North Carolina operate at 345 kV or above. The highest voltage recorded in the state is 500 kV, and the state median is 230 kV.

Who owns the transmission lines at EARLEYS?

The 8 connected lines listed above are owned by VIRGINIA ELECTRIC & POWER CO. Line voltages range from 115 kV to 230 kV. Their combined recorded length is about 112.2 miles.

How do candidate sites near EARLEYS score?

The 8 highest-scoring candidate sites within about 25 miles range from 57 to 60 on the 0–100 DC Readiness scale. They fall in Southampton County, Gates County, Franklin city, Hertford County. The North Carolina average across 2,778 scored sites is 55.1. 1,087 of those North Carolina sites are classed as substation sites (candidate locations generated at an existing substation).

Frequently asked questions

What voltage is EARLEYS substation?

EARLEYS has a maximum voltage of 230 kV. That places it in the 230–344 kV band. The median named US substation in this dataset is 115 kV, so EARLEYS is above the national midpoint.

How many transmission lines connect to EARLEYS substation?

7 transmission lines terminate at or pass through EARLEYS in the HIFLD line data. The connected lines listed here run at 230 kV, 115 kV. Together the listed lines cover about 112.2 miles.

Who owns EARLEYS substation?

HIFLD does not publish substation owners directly. Most of the transmission lines that end at EARLEYS belong to VIRGINIA ELECTRIC & POWER CO. GridCensus derives this from the line data, so confirm ownership with the utility for anything contractual.

Where is EARLEYS substation located?

EARLEYS is in North Carolina at 36.2564, -77.0794. The datacenter candidate sites closest to it are in Southampton County, Gates County, Franklin city.

Are there datacenter candidate sites near EARLEYS substation?

GridCensus lists at least 8 scored candidate sites within roughly 25 miles of EARLEYS. The highest-scoring is BOYKINS at 60/100. Across North Carolina, the average DC Readiness score is 55.1.

Other 230 kV substations in North Carolina

About this data

Source: HIFLD Electric Substations and Transmission Lines (U.S. Department of Homeland Security), as published June 29, 2026. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “EARLEYS substation, North Carolina”, https://gridcensus.com/substations/north-carolina/earleys-5f2124c7 (data as of June 29, 2026).

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

Every site and score for EARLEYS substation, North Carolina is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.