At a glance

NTCQ is a 66 kV electric substation in California, recorded in the HIFLD transmission dataset. 0 transmission lines connect to it. 1,504 of California's 3,003 named substations operate in a higher voltage band. The highest-scoring datacenter candidate site within about 25 miles is MIGUEL in San Diego County, with a DC Readiness score of 61/100.

NTCQ is an electric transmission substation in California. It is classified as distribution (<69 kv) and connects 0 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage66 kV
Voltage classDistribution (<69 kV)
Connected lines0

Ownership

No owner is recorded for the lines that connect here.

Coordinates32.7461, -117.1925

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of NTCQ, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near NTCQ substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
MIGUELSubstation-AdjacentCASan Diego County500 kV1,000 MW7.6 yrs60.6
PENASQUITOSSubstation-AdjacentCASan Diego County230 kV300 MW7.6 yrs57.7
FRIARSSubstation-AdjacentCASan Diego County230 kV300 MW7.6 yrs57.6
MISSIONSubstation-AdjacentCASan Diego County230 kV300 MW7.6 yrs57.6
OLD TOWNSubstation-AdjacentCASan Diego County230 kV300 MW7.6 yrs57.4
STATION FSubstation-AdjacentCASan Diego County230 kV300 MW7.6 yrs57.4
CALPEAK PE 7Substation-AdjacentCASan Diego County230 kV300 MW7.6 yrs57.1
ENCINASubstation-AdjacentCASan Diego County230 kV300 MW7.6 yrs56.8

How does NTCQ compare with other substations in California?

California has 4,260 substation records in HIFLD, of which 3,003 carry a station name; the rest are unnamed tap points, risers and line ends. 1,439 named substations in the state are in NTCQ's below 69 kV band (48% of named stations). 1,504 sit in a higher band. 44 named substations in California operate at 345 kV or above. The highest voltage recorded in the state is 500 kV, and the state median is 69 kV.

How do candidate sites near NTCQ score?

The 8 highest-scoring candidate sites within about 25 miles range from 57 to 61 on the 0–100 DC Readiness scale. They fall in San Diego County. The California average across 8,490 scored sites is 45.4. 1,573 of those California sites are classed as substation sites (candidate locations generated at an existing substation).

Frequently asked questions

What voltage is NTCQ substation?

NTCQ has a maximum voltage of 66 kV. That places it in the below 69 kV band. The median named US substation in this dataset is 115 kV, so NTCQ is below the national midpoint.

How many transmission lines connect to NTCQ substation?

0 transmission lines terminate at or pass through NTCQ in the HIFLD line data.

Where is NTCQ substation located?

NTCQ is in California at 32.7461, -117.1925. The datacenter candidate sites closest to it are in San Diego County.

Are there datacenter candidate sites near NTCQ substation?

GridCensus lists at least 8 scored candidate sites within roughly 25 miles of NTCQ. The highest-scoring is MIGUEL at 61/100. Across California, the average DC Readiness score is 45.4.

Other 66 kV substations in California

About this data

Source: HIFLD Electric Substations and Transmission Lines (U.S. Department of Homeland Security), as published June 29, 2026. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “NTCQ substation, California”, https://gridcensus.com/substations/california/ntcq-0fb0e3d4 (data as of June 29, 2026).

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

Every site and score for NTCQ substation, California is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.