Microsoft Stargate (Mt Pleasant)
DatacenteractiveMount Pleasant, WI · Microsoft
Microsoft Stargate (Mt Pleasant) is an operating datacenter facility in Mount Pleasant, WI, operated by Microsoft. with a catalogued 500 MW of capacity. Existing datacenter clusters are a strong signal for new development: they confirm power availability, fiber peering, and a permitting precedent — which is why nearby candidate sites often inherit the same speed-to-power advantages.
Facility
Nearby internet exchanges
- 324 E WisconsinMilwaukee, WI · 6 networks
- TSR Solutions Data CenterMilwaukee, WI · 5 networks
- Data Holdings MilwaukeeMilwaukee, WI · 2 networks
- TierPoint MilwaukeeMilwaukee, WI · 1 networks
- NETRIX - BBNBannockburn, IL · 1 networks
Other datacenters nearby
- VISAVISA · Vernon Hills, IL
- Pewaukee Data CenterWE Energies · Waukesha, WI
- Expedient MilwaukeeWisconsin CyberLynk Network, Inc. · Franklin, WI
- Datacenter 00919948160WI
- Data Holdings Data CenterStack41, LLC · Milwaukee, WI
Nearby datacenter candidate sites
Scored candidate sites near Microsoft Stargate (Mt Pleasant), ranked by DC Readiness — useful for evaluating expansion or second-site options in the same power/fiber market.
| Site | Type | State | County | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|---|---|
| UNKNOWN121936 | Substation-Adjacent | WI | Kenosha County | 345 kV | 600 MW | 1.4 yrs | 79.1 |
| PLEASANT PRAIRIE | Substation-Adjacent | WI | Kenosha County | 345 kV | 600 MW | 1.4 yrs | 76.9 |
| RACINE | Substation-Adjacent | WI | Racine County | 345 kV | 600 MW | 1.4 yrs | 75.7 |
| OAK CREEK STATION | Substation-Adjacent | WI | Milwaukee County | 345 kV | 600 MW | 1.4 yrs | 75.0 |
| ZION | Substation-Adjacent | WI | Milwaukee County | 345 kV | 600 MW | 1.4 yrs | 74.4 |
| BLUEMOUND | Substation-Adjacent | WI | Milwaukee County | 230 kV | 300 MW | 1.4 yrs | 73.6 |
| Waukegan | Brownfield | IL | Lake | — | 803 MW | — | 73.0 |
| BAIN | Substation-Adjacent | WI | Kenosha County | 345 kV | 600 MW | 1.4 yrs | 72.8 |
Dataset updated . Screening estimates derived from public data sources.
Datacenter records are derived from public facility datasets (PNNL and related sources) and may be incomplete or lag operational changes. Capacity and footprint are catalogued estimates — confirm operator, capacity, and availability directly with the facility.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Microsoft Stargate (Mt Pleasant), Mount Pleasant, WI. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.