EC Near Osage (WY)

Greenfield

Weston, Wyoming · WECC

DC Readiness
55.1
Good / 100

EC Near Osage (WY) is a greenfield datacenter candidate site in Weston, Wyoming, interconnecting through WECC. It screens at 55.1/100 DC Readiness and a 1.7 yrs average interconnection-queue wait.

Power & interconnection

Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionWECC
Queue depth74
Avg queue wait1.7 yrs
Recent queue wait1.0 yrs
Completion rate17%
Withdrawal rate84%

Connectivity

Nearest IXPGolden West Rapid City Skyline Facility
IXP distance59.1 mi
Fiber providers4
Fiber coverage42.2%
Nearest cloud providerGCP
Nearest cloud regionus-west3
Cloud region distance438.5 mi

Site characteristics

Site typeGreenfield
Parcel ownerBLACK HILLS POWER, INC.
Land owner typeprivate
Buildability50.0/100
Former usenear retired coal plant (10km)

Risk & environment

Flood zoneZone X
Water stress (WRI)2.60
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score90/100
Construction cost index87.2 (avg 100)

Location context

Nearest datacenterGolden West Rapid City Skyline Facility
DC distance59.1 mi
Nearest rail4.0 mi
Nearest gas pipeline2.3 mi
Nearest fiber route144.5 mi
County hazard (FEMA NRI)Very Low (10)
DC tax incentiveYes (no_income_tax)
Commercial electricity10.68¢/kWh
Industrial electricity8.14¢/kWh
Cooling degree days300
Heating degree days7,600
Land price / acre$953

Incentive detail: No state corporate or personal income tax; low property taxes.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
31
Fiber connectivity12%
59
Energy cost10%
94
Water risk8%
48
Natural hazard8%
90
Buildability7%
50
Labor market4%
50
DC cluster4%
40
Land / acreage3%
54
Construction cost3%
77
Gas pipeline2%
93
Tax incentive2%
100
Climate / cooling2%
100

Nearby comparable sites

Other scored datacenter candidate sites in Weston, ranked by DC Readiness.

Sites near EC Near Osage (WY)
SiteTypeVoltageCapacityQueue waitScore
TAP205630Substation-Adjacent230 kV300 MW1.7 yrs68.3
UNKNOWN201481Substation-Adjacent230 kV300 MW1.7 yrs67.7
TAP203672Substation-Adjacent230 kV300 MW1.7 yrs66.8
TECKLASubstation-Adjacent230 kV300 MW1.7 yrs66.6
TAP204301Substation-Adjacent115 kV100 MW1.7 yrs63.6
UNKNOWN204407Substation-Adjacent115 kV100 MW1.7 yrs63.6
UNKNOWN205633Substation-Adjacent115 kV100 MW1.7 yrs63.3
UNKNOWN205116Substation-Adjacent115 kV100 MW1.7 yrs62.8

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.