Federal Excess

Converse County, Wyoming · WECC

DC Readiness
53.8
Fair / 100

Glendo (P-S) is a federal excess datacenter candidate site in Converse County, Wyoming, interconnecting through WECC. It screens at 53.8/100 DC Readiness and a 6.9 yrs average interconnection-queue wait.

Power & interconnection

Speed to power

Interconnection outlookConstrained
≈ 6.9 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionWECC
Queue depth34
Avg queue wait6.9 yrs

Connectivity

Nearest IXPACT Douglas
IXP distance14.1 mi
Fiber providers4
Fiber coverage31.0%

Site characteristics

Acreage201 ac
Buildable load (est.)~80–201 MWland-based
Land contactConverse County County Assessor
Former useReclamation and Irrigation

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Medium-High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score90/100

Location context

Nearest datacenterACT Douglas
DC distance14.1 mi
County hazard (FEMA NRI)Very Low (10)
DC tax incentiveYes (no_income_tax)
Commercial electricity10.28¢/kWh
Industrial electricity7.70¢/kWh
Cooling degree days300
Heating degree days7,600
Land price / acre$709

Regulatory climate

Favorablestate posture · as of 2026-08

Low-cost power and land; DC-friendly posture.

DC tax incentiveYes

Incentive detail: No state corporate or personal income tax; low property taxes.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Glendo (P-S)

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
55
Fiber connectivity12%
72
Energy cost10%
50
Water risk7%
48
Natural hazard6%
90
Buildability7%
50
Labor market4%
50
DC cluster4%
80
Land / acreage3%
70
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
100

Nearby comparable sites

Other scored datacenter candidate sites in Converse County, ranked by DC Readiness.

Sites near Glendo (P-S)
SiteTypeVoltageCapacityQueue waitScore
Dave Johnston Mine / Rolling HillsBrownfield115 kV119 MW6.9 yrs65.0
EC Coal Converse CountyGreenfield——1.7 yrs64.1
EC Coal Converse CountyGreenfield——1.7 yrs64.0
LATIGOSubstation-Adjacent230 kV300 MW6.9 yrs62.3
TAP208905Substation-Adjacent230 kV300 MW6.9 yrs62.0
UNKNOWN201361Substation-Adjacent230 kV300 MW6.9 yrs62.0
WINDSTARSubstation-Adjacent230 kV300 MW6.9 yrs61.9
UNKNOWN201486Substation-Adjacent230 kV300 MW6.9 yrs61.5

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Glendo (P-S), Converse County. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.