Sinclair Substation at 41.781, -107.119

Federal Excess

Carbon County, Wyoming · WECC

DC Readiness
47.2
Fair / 100

At a glance

Sinclair Substation at 41.781, -107.119 is a federal excess datacenter candidate site in Carbon County, Wyoming, scoring 47.2/100 DC Readiness — 81st of 99 scored sites in the county. It sits in the WECC grid region, where interconnection has averaged 3.5 years from request to operation.

Power & interconnection

Speed to power

Interconnection outlookConstrained
≈ 5.5 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionWECC
Queue depth34
Avg queue wait3.5 yrs
Recent queue wait5.5 yrs
Completion rate17%
Withdrawal rate84%

Connectivity

Nearest IXPMountain West Technologies - Casper
IXP distance84.2 mi
Fiber providers3
Fiber coverage16.7%
Max download9 Mbps

Site characteristics

Acreage10 ac
Buildable load (est.)~4–10 MWland-based
Former usePower Development and Distribution

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Medium-High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score90/100

Location context

Nearest datacenterMountain West Technologies - Casper
DC distance84.2 mi
County hazard (FEMA NRI)Very Low (10)
DC tax incentiveYes (no_income_tax)
Commercial electricity11.57¢/kWh
Industrial electricity7.86¢/kWh
Cooling degree days300
Heating degree days7,600
Land price / acre$971

Regulatory climate

Favorablestate posture · as of 2026-08

Low-cost power and land; DC-friendly posture.

DC tax incentiveYes

Incentive detail: No state corporate or personal income tax; low property taxes.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Sinclair Substation

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

How does Sinclair Substation at 41.781, -107.119 compare with other sites in Carbon County?

Sinclair Substation at 41.781, -107.119 ranks 81st of 99 scored candidate sites in Carbon County. Its 47.2/100 is roughly in line with the county average of 50.1. It is roughly in line with the Wyoming average of 52.2 and about 11% below the national average of 53.2.

Against the Wyoming average, its strongest sub-score is natural hazard (90 vs 89) and its weakest is power availability (30 vs 38). Power and speed to power each carry 20% of the composite score, fiber 12%, water 7% and hazard 6%.

How close is Sinclair Substation at 41.781, -107.119 to power, fiber and other datacenters?

For connectivity, the nearest internet exchange facility is Mountain West Technologies - Casper at 84.2 miles. 3 fiber providers report service at the location in FCC broadband data. The closest operating datacenter on record is Mountain West Technologies - Casper, 84.2 miles away.

What are the flood, water and hazard risks at Sinclair Substation at 41.781, -107.119?

At the county level, FEMA's National Risk Index rates Carbon County "Very Low".

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
49
Fiber connectivity12%
54
Energy cost10%
50
Water risk7%
48
Natural hazard6%
90
Buildability7%
50
Labor market4%
50
DC cluster4%
20
Land / acreage3%
43
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
100

Nearby comparable sites

Other scored datacenter candidate sites in Carbon County, ranked by DC Readiness.

Sites near Sinclair Substation at 41.781, -107.119
SiteTypeVoltageCapacityQueue waitScore
Sinclair Oil RefineryBrownfield—5 MW3.5 yrs61.1
SEMINOESubstation-Adjacent230 kV300 MW4.3 yrs58.7
UNKNOWN201479Substation-Adjacent230 kV300 MW4.3 yrs58.6
FREEZEOUTSubstation-Adjacent230 kV300 MW3.5 yrs58.4
UNKNOWN202491Substation-Adjacent230 kV300 MW4.3 yrs58.3
UNKNOWN201482Substation-Adjacent230 kV300 MW3.5 yrs57.9
MINERSSubstation-Adjacent230 kV300 MW3.5 yrs57.9
ECHO SPRINGSSubstation-Adjacent230 kV300 MW3.5 yrs57.7

Sinclair Substation at 41.781, -107.119: common questions

What is the DC Readiness score of Sinclair Substation at 41.781, -107.119?

Sinclair Substation at 41.781, -107.119 scores 47.2/100 on the GridCensus DC Readiness scale, rated fair. It ranks 81st of 99 scored sites in Carbon County. The Carbon County average is 50.1 and the Wyoming average is 52.2.

What grid region is Sinclair Substation at 41.781, -107.119 in?

Sinclair Substation at 41.781, -107.119 is in the WECC region. Projects interconnecting there have averaged a 3.5-year wait from queue request to operation.

How far is Sinclair Substation at 41.781, -107.119 from an internet exchange?

The nearest internet exchange facility is Mountain West Technologies - Casper, about 84.2 miles away; 3 fiber providers report service at the location.

Related pages

About this data

Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published October 10, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “Sinclair Substation at 41.781, -107.119, Carbon County, WY”, https://gridcensus.com/datacenter-sites/wyoming/carbon-county/sinclair-substation-87c95283 (data as of October 10, 2026).

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for Sinclair Substation at 41.781, -107.119, Carbon County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.