Skip to content
Gridcensus

EC Coal Campbell County

Greenfield

Campbell County, Wyoming · WECC

DC Readiness
62.2
Good / 100

EC Coal Campbell County is a greenfield datacenter candidate site in Campbell County, Wyoming, interconnecting through WECC. It screens at 62.2/100 DC Readiness and a 1.7 yrs average interconnection-queue wait.

Power & interconnection

Utility commercial rate0.09¢/kWh
UtilityPOWDER RIVER ENERGY CORPcooperativefavorable to large load · state default

Speed to power

Interconnection outlookFavorable
≈ 1.0 yrs typical interconnection wait

Shorter queues and healthier completion here — a faster path to energization than the national norm.

ISO / RTO regionWECC
Queue depth34
Avg queue wait1.7 yrs
Recent queue wait1.0 yrs
Completion rate17%
Withdrawal rate84%

Connectivity

Nearest IXPACT Gillette
IXP distance25.1 mi
Fiber providers6
Fiber coverage51.2%
Nearest cloud providerGCP
Nearest cloud regionus-west3
Cloud region distance399.8 mi

Site characteristics

Site typeGreenfield
Land contactCampbell County County Assessor
Land owner typeprivate
Buildability80.0/100
Land cover (NLCD)Grassland/Herbaceous
Former usecoal mine

Risk & environment

Environmental constraintNone (0/100)
Flood zoneZone X
Water stress (WRI)2.60
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score90/100
Construction cost index94.7 (avg 100)

Location context

Nearest datacenterDatacenter 1414729942
DC distance24.2 mi
Nearest rail1.8 mi
Nearest gas pipeline3.9 mi
Nearest fiber route164.7 mi
County hazard (FEMA NRI)Very Low (10)
DC tax incentiveYes (no_income_tax)
Commercial electricity9.23¢/kWh
Industrial electricity7.25¢/kWh
Cooling degree days300
Heating degree days7,600
Land price / acre$959

Regulatory climate

Favorablestate posture · as of 2026-08

Low-cost power and land; DC-friendly posture.

DC tax incentiveYes

Incentive detail: No state corporate or personal income tax; low property taxes.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track EC Coal Campbell County

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
61
Fiber connectivity12%
68
Energy cost10%
94
Water risk7%
50
Natural hazard6%
90
Buildability7%
80
Labor market4%
50
DC cluster4%
60
Land / acreage3%
55
Construction cost3%
71
Gas pipeline2%
88
Tax incentive1%
100
Climate / cooling1%
100

Nearby comparable sites

Other scored datacenter candidate sites in Campbell County, ranked by DC Readiness.

Sites near EC Coal Campbell County
SiteTypeVoltageCapacityQueue waitScore
EC Near Neil SimpsonGreenfield——1.7 yrs65.7
EC Near Neil SimpsonGreenfield——1.7 yrs65.2
EC Near Neil SimpsonGreenfield——1.7 yrs65.2
EC Near Neil SimpsonGreenfield——1.7 yrs65.2
UNKNOWN201359Substation-Adjacent230 kV300 MW6.9 yrs65.1
UNKNOWN204384Substation-Adjacent230 kV300 MW6.9 yrs64.9
UNKNOWN201476Substation-Adjacent230 kV300 MW6.9 yrs64.8
EC Coal Campbell CountyGreenfield——1.7 yrs64.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for EC Coal Campbell County, Campbell County. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.