Former Barton Products/Prism Manufacturing Property

Industrial

Washington, Wisconsin · MISO

DC Readiness
50.4
Fair / 100

Former Barton Products/Prism Manufacturing Property is an industrial datacenter candidate site in Washington, Wisconsin, interconnecting through MISO. It screens at 50.4/100 DC Readiness and a 4.3 yrs average interconnection-queue wait.

Power & interconnection

UtilityWISCONSIN ELECTRIC POWER COinvestor ownedfavorable to large load · terms ≥ 100 MWVery Large Customer (VLC) tariff · 10 yr

Speed to power

Interconnection outlookModerate
≈ 4.9 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionMISO
Queue depth133
Avg queue wait4.3 yrs
Recent queue wait4.9 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPEthoplex Data Center
IXP distance9.9 mi
Fiber providers7
Fiber coverage27.8%

Site characteristics

Site typeIndustrial
Land contactWashington County County Assessor

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score78/100

Location context

Nearest datacenterEthoplex Data Center
DC distance9.9 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity13.21¢/kWh
Industrial electricity9.16¢/kWh
Cooling degree days600
Heating degree days7,200
Land price / acre$9,471

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Enterprise Zone tax credits; TIF available for DC construction in eligible areas.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Former Barton Products/Prism Manufacturing Property

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
48
Fiber connectivity12%
40
Energy cost10%
50
Water risk7%
94
Natural hazard6%
78
Buildability7%
50
Labor market4%
50
DC cluster4%
80
Land / acreage3%
45
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
95

Nearby comparable sites

Other scored datacenter candidate sites in Washington, ranked by DC Readiness.

Sites near Former Barton Products/Prism Manufacturing Property
SiteTypeVoltageCapacityQueue waitScore
TAP138061Substation-Adjacent345 kV600 MW4.3 yrs66.4
EC Near Omega Hills Gas RecoveryGreenfield——4.3 yrs64.2
EC Near Omega Hills Gas RecoveryGreenfield——4.3 yrs63.2
EC Near WPPI Hartford DGGreenfield——4.3 yrs62.9
GERMANTOWN SW YDSubstation-Adjacent138 kV100 MW4.3 yrs62.4
68TH STREETSubstation-Adjacent138 kV100 MW4.3 yrs61.0
PLEASANT VALLEYSubstation-Adjacent138 kV100 MW4.3 yrs60.9
CEDARBURG SOUTHSubstation-Adjacent138 kV100 MW4.3 yrs60.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for Former Barton Products/Prism Manufacturing Property, Washington is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.