EC Coal Henrico County

Greenfield

Henrico, Virginia · PJM

DC Readiness
57.1
Good / 100

EC Coal Henrico County is a greenfield datacenter candidate site in Henrico, Virginia, interconnecting through PJM. It screens at 57.1/100 DC Readiness and a 3.1 yrs average interconnection-queue wait.

Power & interconnection

LMP zonePJM_DOM
Wholesale LMP$43.92/MWh
Utility commercial rate0.05¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth864
Avg queue wait3.1 yrs
Recent queue wait3.6 yrs
Completion rate20%
Withdrawal rate80%

Connectivity

Nearest IXPQTS Richmond (RIC1)
IXP distance4.4 mi
Fiber providers4
Fiber coverage90.7%
Nearest cloud providerAzure
Nearest cloud regioneastus2
Cloud region distance81.3 mi

Site characteristics

Site typeGreenfield
Parcel ownerVIRGINIA ELECTRIC & POWER CO
Land owner typeprivate
Buildability50.0/100
Land cover (NLCD)Mixed Forest
Former usecoal adjacent

Risk & environment

Flood zoneZone X
Water stress (WRI)0.60
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score70/100
Construction cost index99.9 (avg 100)

Location context

Nearest datacenterMeta Henrico Data Center
DC distance4.0 mi
Nearest rail3.4 mi
Nearest gas pipeline5.0 mi
Nearest fiber route65.9 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity4.81¢/kWh
Industrial electricity4.19¢/kWh
Cooling degree days1,300
Heating degree days4,000
Land price / acre$7,750

Incentive detail: Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
44
Fiber connectivity12%
51
Energy cost10%
83
Water risk8%
88
Natural hazard8%
70
Buildability7%
50
Labor market4%
50
DC cluster4%
90
Land / acreage3%
46
Construction cost3%
67
Gas pipeline2%
84
Tax incentive2%
100
Climate / cooling2%
60

Nearby comparable sites

Other scored datacenter candidate sites in Henrico, ranked by DC Readiness.

Sites near EC Coal Henrico County
SiteTypeVoltageCapacityQueue waitScore
Greenfield (ELMONT - CHICKAHOMINY)Greenfield500 kV1,000 MW3.1 yrs75.3
CHESTERFIELDSubstation-Adjacent230 kV300 MW3.1 yrs75.0
TURNER ROADSubstation-Adjacent230 kV300 MW3.1 yrs74.4
TAP147581Substation-Adjacent230 kV300 MW3.1 yrs74.3
ELKOSubstation-Adjacent230 kV300 MW3.1 yrs73.4
DARBYTOWN CTSSubstation-Adjacent230 kV300 MW3.1 yrs72.5
Greenfield (ELMONT - CHICKAHOMINY)Greenfield500 kV1,000 MW3.1 yrs71.6
TAP147861Substation-Adjacent115 kV100 MW3.1 yrs69.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for EC Coal Henrico County, Henrico. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.