FISHER DIAGNOSTICS (IN-VITRO DIAGNOSTIC SUBSTANCE MANUFACTURING)

Manufacturing

FREDERICK, Virginia

DC Readiness
54.2
Fair / 100

FISHER DIAGNOSTICS (IN-VITRO DIAGNOSTIC SUBSTANCE MANUFACTURING) is a manufacturing datacenter candidate site in FREDERICK, Virginia. It screens at 54.2/100 DC Readiness and a 3.5 yrs average interconnection-queue wait.

Power & interconnection

UtilityRAPPAHANNOCK ELECTRIC COOPcooperativemoderate to large load · terms ≥ 25 MW

Speed to power

Interconnection outlookModerate
≈ 3.5 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

Avg queue wait3.5 yrs

Connectivity

Nearest IXPDigital Realty GNV (8217 Linton Hall)
IXP distance41.1 mi
Fiber providers7
Fiber coverage52.7%

Site characteristics

Site typeManufacturing
Land contactFREDERICK County Assessor

Risk & environment

Environmental constraintNone (0/100)
Flood zoneZone X
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score70/100

Location context

Nearest datacenterMiddletown Data Center
DC distance0.1 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.20¢/kWh
Industrial electricity8.97¢/kWh
Cooling degree days1,300
Heating degree days4,000
Land price / acre$7,861

Regulatory climate

Moderatestate posture · as of 2026-08

Largest US DC market; incentive preserved but a new $0.011/kWh DC electricity tax starts Jul 2026.

DC tax incentiveYes
Large-load threshold≥ 25 MW

Dominion GS-5 large-load rate (≥25 MW, ~$1.5M/MW collateral, 14-yr term) effective 2027.

Incentive detail: Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track FISHER DIAGNOSTICS (IN-VITRO DIAGNOSTIC SUBSTANCE MANUFACTURING)

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
55
Fiber connectivity12%
65
Energy cost10%
50
Water risk7%
88
Natural hazard6%
70
Buildability7%
50
Labor market4%
50
DC cluster4%
100
Land / acreage3%
46
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
60

Nearby comparable sites

Other scored datacenter candidate sites in FREDERICK, ranked by DC Readiness.

Sites near FISHER DIAGNOSTICS (IN-VITRO DIAGNOSTIC SUBSTANCE MANUFACTURING)
SiteTypeVoltageCapacityQueue waitScore
OZ FrederickGreenfield——3.1 yrs61.6
CHEMSTONE CORP. (CUT STONE AND STONE PRODUCT MANUFACTURING)Manufacturing——3.5 yrs54.3
TABARD CORP. (OTHER SNACK FOOD MANUFACTURING)Manufacturing——3.5 yrs54.2
VALLEY TRADER (PREPRESS SERVICES)Manufacturing——3.5 yrs54.2
STOWE-WOODWARD, INC. (ALL OTHER RUBBER PRODUCT MANUFACTURING)Manufacturing——3.5 yrs54.2
CRIDER & SHOCKEY, INC. (READY-MIX CONCRETE MANUFACTURING)Manufacturing——3.5 yrs53.5
SOUTHEASTERN CONTAINER, INC. (PLASTICS BOTTLE MANUFACTURING)Manufacturing——3.5 yrs53.5
KINGSDOWN, INC. (MATTRESS MANUFACTURING)Manufacturing——3.5 yrs53.5

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for FISHER DIAGNOSTICS (IN-VITRO DIAGNOSTIC SUBSTANCE MANUFACTURING), FREDERICK. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.