Skip to content
Gridcensus

Mine Site

Former Mine

Windsor County, Vermont · ISO-NE

DC Readiness
51.5
Fair / 100

Mine Site is a former mine datacenter candidate site in Windsor County, Vermont, interconnecting through ISO-NE. It screens at 51.5/100 DC Readiness and a 3.9 yrs average interconnection-queue wait.

Power & interconnection

UtilityGREEN MOUNTAIN POWER CORPinvestor ownedmoderate to large load · terms ≥ 25 MW

Speed to power

Interconnection outlookModerate
≈ 3.9 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionISO-NE
Queue depth5
Avg queue wait3.9 yrs

Connectivity

Nearest IXPVELCO Rutland
IXP distance25.3 mi
Fiber providers7
Fiber coverage87.0%

Site characteristics

Site typeFormer Mine
Former useMining: SandAndGravel; Status: Abandoned
Cleanup statusAbandoned

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score85/100

Location context

Nearest datacenterVELCO Rutland
DC distance25.3 mi
County hazard (FEMA NRI)Relatively Low (15)
DC tax incentiveNo
Commercial electricity19.25¢/kWh
Industrial electricity10.84¢/kWh
Cooling degree days400
Heating degree days7,400
Land price / acre$4,863

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Mine Site

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
36
Fiber connectivity12%
79
Energy cost10%
50
Water risk7%
94
Natural hazard6%
85
Buildability7%
50
Labor market4%
50
DC cluster4%
60
Land / acreage3%
49
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
0
Climate / cooling1%
100

Nearby comparable sites

Other scored datacenter candidate sites in Windsor County, ranked by DC Readiness.

Sites near Mine Site
SiteTypeVoltageCapacityQueue waitScore
COOLIDGESubstation-Adjacent345 kV600 MW3.9 yrs63.9
OZ WindsorGreenfield——3.5 yrs58.0
UNKNOWN132698Substation-Adjacent115 kV100 MW3.9 yrs57.0
UNKNOWN132753Substation-Adjacent115 kV100 MW3.9 yrs57.0
WILDERSubstation-Adjacent115 kV100 MW3.9 yrs56.1
UNKNOWN133752Substation-Adjacent115 kV100 MW3.9 yrs56.1
WINDSORSubstation-Adjacent115 kV100 MW3.9 yrs56.1
OZ WindsorGreenfield——3.5 yrs54.0

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.