OZ Chittenden

Greenfield

Chittenden County, Vermont · ISO-NE

DC Readiness
65.4
Good / 100

OZ Chittenden is a greenfield datacenter candidate site in Chittenden County, Vermont, interconnecting through ISO-NE. It screens at 65.4/100 DC Readiness and a 3.5 yrs average interconnection-queue wait.

Power & interconnection

LMP zoneISONE_VT
Wholesale LMP$69.07/MWh
Utility commercial rate0.19¢/kWh

Speed to power

ISO / RTO regionISO-NE
Queue depth3
Avg queue wait3.5 yrs
Recent queue wait3.5 yrs
Completion rate25%
Withdrawal rate75%

Connectivity

Nearest IXPSoVerNet Burlington
IXP distance1.6 mi
Fiber providers7
Fiber coverage55.0%
Nearest cloud providerAWS
Nearest cloud regionus-east-1
Cloud region distance436.9 mi

Site characteristics

Site typeGreenfield
Parcel ownerHat-Trick Properties
Land owner typeprivate
Buildability92.0/100
Land cover (NLCD)Developed, Low Intensity

Risk & environment

Flood zoneZone X
Water stress (WRI)0.30
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteHHWC CSWD WINOOSKI LANDRY PARK
Hazard sub-score75/100
Construction cost index97.9 (avg 100)

Location context

Nearest datacenterSoVerNet Burlington
DC distance1.6 mi
Nearest rail0.7 mi
Nearest gas pipeline0.9 mi
Nearest fiber route94.6 mi
County hazard (FEMA NRI)Relatively Low (15)
DC tax incentiveNo
Commercial electricity18.69¢/kWh
Industrial electricity12.08¢/kWh
Cooling degree days400
Heating degree days7,400
Land price / acre$6,230

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
54
Fiber connectivity12%
90
Energy cost10%
70
Water risk8%
96
Natural hazard8%
75
Buildability7%
92
Labor market4%
50
DC cluster4%
100
Land / acreage3%
49
Construction cost3%
68
Gas pipeline2%
97
Tax incentive2%
0
Climate / cooling2%
100

Nearby comparable sites

Other scored datacenter candidate sites in Chittenden County, ranked by DC Readiness.

Sites near OZ Chittenden
SiteTypeVoltageCapacityQueue waitScore
South Burlington LandfillBrownfield2 MW68.2
UNKNOWN132786Substation-Adjacent115 kV100 MW3.5 yrs67.1
QUEEN CITYSubstation-Adjacent115 kV100 MW3.5 yrs66.6
TAP136809Substation-Adjacent115 kV100 MW3.5 yrs66.1
WILLISTONSubstation-Adjacent115 kV100 MW3.5 yrs66.0
SAND BARSubstation-Adjacent115 kV100 MW3.5 yrs65.0
TAP139871Substation-Adjacent115 kV100 MW3.5 yrs64.2
EC Near Essex Junction 19Greenfield3.5 yrs63.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.