Skip to content
Gridcensus

UNKNOWN209693

Substation-Adjacent

Tooele County, Utah · WECC

DC Readiness
50.5
Fair / 100

UNKNOWN209693 is a substation-adjacent datacenter candidate site in Tooele County, Utah, interconnecting through WECC. It screens at 50.5/100 DC Readiness with a catalogued 50 MW of candidate capacity and a 3.5 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN209693
Substation distance0.0 mi
Substation voltage69 kV
Available capacity50 MW

Speed to power

Interconnection outlookConstrained
≈ 5.5 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionWECC
Queue depth34
Avg queue wait3.5 yrs
Recent queue wait5.5 yrs
Completion rate17%
Withdrawal rate84%

Connectivity

Nearest IXPDataBank Salt Lake City (SLC3)
IXP distance50.1 mi
Fiber providers9
Fiber coverage67.8%

Site characteristics

Land contactTooele County County Assessor

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score85/100

Location context

Nearest datacenterDatacenter 01473440674
DC distance40.6 mi
County hazard (FEMA NRI)Relatively Low (15)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity9.56¢/kWh
Industrial electricity7.55¢/kWh
Cooling degree days1,000
Heating degree days5,500
Land price / acre$3,447

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Enterprise Zone tax credits; Economic Development Tax Increment Financing (EDTIF).

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track UNKNOWN209693

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
46
Speed to power20%
51
Fiber connectivity12%
54
Energy cost10%
50
Water risk7%
24
Natural hazard6%
85
Buildability7%
60
Labor market4%
50
DC cluster4%
40
Land / acreage3%
51
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
75

Nearby comparable sites

Other scored datacenter candidate sites in Tooele County, ranked by DC Readiness.

Sites near UNKNOWN209693
SiteTypeVoltageCapacityQueue waitScore
EC Coal Tooele CountyGreenfield——3.5 yrs62.2
OZ TooeleGreenfield——3.5 yrs59.7
EC Near US MagnesiumGreenfield——3.5 yrs55.7
EC Near US MagnesiumGreenfield——3.5 yrs55.1
EC Near US MagnesiumGreenfield——3.5 yrs55.0
EC Near US MagnesiumGreenfield——3.5 yrs55.0
UNKNOWN202988Substation-Adjacent115 kV100 MW3.5 yrs54.3
TAP206145Substation-Adjacent115 kV100 MW3.5 yrs54.3

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for UNKNOWN209693, Tooele County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.