Skip to content
Gridcensus

Emery County, Utah · WECC

DC Readiness
48.6
Fair / 100

TAP208885 is a substation-adjacent datacenter candidate site in Emery County, Utah, interconnecting through WECC. It screens at 48.6/100 DC Readiness with a catalogued 50 MW of candidate capacity and a 6.9 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTAP208885
Substation distance0.0 mi
Substation voltage69 kV
Available capacity50 MW

Speed to power

ISO / RTO regionWECC
Queue depth34
Avg queue wait6.9 yrs

Connectivity

Nearest IXPVoonami SLC1
IXP distance83.2 mi
Fiber providers1
Fiber coverage95.9%

Site characteristics

Risk & environment

Water stress (WRI)High
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score85/100

Location context

Nearest datacenterVoonami SLC1
DC distance83.2 mi
County hazard (FEMA NRI)Relatively Low (15)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity9.52¢/kWh
Industrial electricity7.63¢/kWh
Cooling degree days1,000
Heating degree days5,500
Land price / acre$6,319

Incentive detail: Enterprise Zone tax credits; Economic Development Tax Increment Financing (EDTIF).

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
46
Speed to power15%
44
Fiber connectivity12%
44
Energy cost10%
50
Water risk8%
24
Natural hazard8%
85
Buildability7%
60
Labor market4%
50
DC cluster4%
20
Land / acreage3%
51
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in Emery County, ranked by DC Readiness.

Sites near TAP208885
SiteTypeVoltageCapacityQueue waitScore
EC Coal Emery CountyGreenfield1.7 yrs59.5
EC Coal Emery CountyGreenfield1.7 yrs57.4
EMERYSubstation-Adjacent345 kV600 MW6.9 yrs56.8
EC Coal Emery CountyGreenfield1.7 yrs56.7
MCFADDENSubstation-Adjacent138 kV100 MW6.9 yrs51.0
Mine SiteFormer Mine6.9 yrs48.7
UNKNOWN207905Substation-Adjacent69 kV50 MW6.9 yrs48.6
UNKNOWN207912Substation-Adjacent69 kV50 MW6.9 yrs48.6

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP208885, Emery County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.