Emery County, Utah · WECC

DC Readiness
56.8
Good / 100

EMERY is a substation-adjacent datacenter candidate site in Emery County, Utah, interconnecting through WECC. It screens at 56.8/100 DC Readiness with a catalogued 600 MW of candidate capacity and a 6.9 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationEMERY
Substation distance0.0 mi
Substation voltage345 kV
Available capacity600 MW

Speed to power

ISO / RTO regionWECC
Queue depth34
Avg queue wait6.9 yrs

Connectivity

Nearest IXPVoonami SLC1
IXP distance86.6 mi
Fiber providers1
Fiber coverage95.9%

Site characteristics

Land contactEmery County County Assessor

Risk & environment

Water stress (WRI)High
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score85/100

Location context

Nearest datacenterVoonami SLC1
DC distance86.6 mi
County hazard (FEMA NRI)Relatively Low (15)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity9.52¢/kWh
Industrial electricity7.63¢/kWh
Cooling degree days1,000
Heating degree days5,500
Land price / acre$6,319

Incentive detail: Enterprise Zone tax credits; Economic Development Tax Increment Financing (EDTIF).

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
87
Speed to power15%
44
Fiber connectivity12%
44
Energy cost10%
50
Water risk8%
24
Natural hazard8%
85
Buildability7%
60
Labor market4%
50
DC cluster4%
20
Land / acreage3%
51
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in Emery County, ranked by DC Readiness.

Sites near EMERY
SiteTypeVoltageCapacityQueue waitScore
EC Coal Emery CountyGreenfield1.7 yrs59.5
EC Coal Emery CountyGreenfield1.7 yrs57.4
EC Coal Emery CountyGreenfield1.7 yrs56.7
MCFADDENSubstation-Adjacent138 kV100 MW6.9 yrs51.0
Mine SiteFormer Mine6.9 yrs48.7
UNKNOWN207911Substation-Adjacent69 kV50 MW6.9 yrs48.6
UNKNOWN207905Substation-Adjacent69 kV50 MW6.9 yrs48.6
UNKNOWN207912Substation-Adjacent69 kV50 MW6.9 yrs48.6

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for EMERY, Emery County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.